Rainwater Management

NC-v4 SSc4:Rainwater management
posted by  Hadar Farjo  on 

We our developing a brownfield site.There is no annual increase in runoff volume from the pre development cover condition to the post developed condition.

1
Fri Jul 14, 2017, 2:42 pm

Retro-Enhanced Commissioning

NC-2009 EAc3:Enhanced Commissioning
posted by  Christian Pegher  on 

Our project is on hold until the fall. The construction documents are done, and the owner just hired a CxA. They'd like to have the CxA go back through the documents now and provide feedback.

1
Sat Aug 5, 2017, 5:08 pm

Elevated buggy paths qand bridges for resort projecct

NC-2009 SSc7.1:Heat Island Effect—Non-Roof
posted by  John Covello  on 

Hello, I am dealing with a hotel project that will have elevated buggy paths connected to buildings for a second and third tier of buildings.

1
Mon Jul 17, 2017, 9:10 am

How can I develop leed certificate service in my country?

NC-v4 EQp1:Minimum indoor air quality performance
posted by  erdem özkan  on 

We provide Leed certificate and green building service but how are we developing this process in Turkey?

0

Cooling Tower

CI-2009 SSc1:Site Selection
posted by  Kristopher Croghan  on 

Our CI client owns the building they're in and are looking for additional water savings, beyond the water savings as outlined in LEED CI WEc1.

1
Sat Aug 26, 2017, 10:42 pm

Certify only one floor among three floors that are rented

CI-v4 MPR2:Must use reasonable LEED boundaries
posted by  Diana Nezamutinova  on 

Would you please advise if one newly acquired floor of a 3-floor office eligible to get certified under LEED v.4 Commercial Interiors (see details below)? - A company XYZ has been renting 2 adjac

1
Sat Aug 26, 2017, 6:01 pm

Arc Skoru update

General forums
posted by  Bill Swanson  on 

Hey Tristan, any update on this LEED Dynamic Plaque? Last year there was a lot of pressure made to convert as many LEED credits into "dynamic" points for use in this plaque.

0

LEED Certification for a portion of a building

NC-v4 MPR2:Must use reasonable LEED boundaries
posted by  Eesmyal Santos-Brault  on 

Hi there, I am working on a 17 storey residential project with social housing on the podium levels (3 storey). The social housing part has a separate entrance, mechanical and electrical systems.

1
Thu Jun 22, 2017, 10:02 am

Overhangs and light transmittance vrs daylighting

CI-v4 EAp2:Minimum energy performance
posted by  Gustav Alfaro  on 

Hi everyone, This office tenant space is located in a building with large overhangs and the visible transmittance through the windows is poor, we ran daylight simulations and it seems that the lig

1
Thu Jun 22, 2017, 1:00 pm

Furniture heights

CI-v4 EQc8:Quality views
posted by  Subramaniam Chandrasekaran  on 

exactly same as the below mentioned point; for a project, the interior designer wants to know whether they have to go with 1050 mm or 1100 mm of workstation height; this clarification answers; but

1
Mon Jul 10, 2017, 12:43 pm