We our developing a brownfield site.There is no annual increase in runoff volume from the pre development cover condition to the post developed condition. The site runoff will be discharged through storm pipe to an existing Pond (outside the project LEED boundary) that was designed to accommodate and manage the runoff. Do will be able to achieve the credit based on this.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Michael DeVuono
Regional Stormwater LeaderArcadis North America
LEEDuser Expert
188 thumbs up
July 14, 2017 - 10:42 am
I have a hard time believing this....are you modelling the pre-development as the site appeared in the stone age, or as it existed a month prior to the start of your project?