Performance Period
posted by  Sarfaraj Khan  on 

Hi Did any one know any guideline or book from USGBC to complete the project documents for LEED V4 O&M in the Arc Platform if the project is going for performance pathway

1
Wed Apr 12, 2017, 2:45 pm

Vegetation under solar panels

NC-2009 SSc5.1:Site Development—Protect or Restore Habitat
posted by  Cesar Ruiz  on 

Hello, We are working on a project which is going to have almost all of its roof covered by solar panels.

1
Tue Apr 11, 2017, 8:05 pm

Free Address vs. Full Flexibility

WELL v1 Building Standard Tip Sheet
posted by  Carina Clark  on 

WELL's Intent for feature 82 Individual Thermal Comfort is: To maximize and personalize thermal comfort among all occupants.

1
Thu Sep 7, 2017, 7:56 pm

A partial ceiling area was affected by mold

Schools-2009 IEQc10:Mold Prevention
posted by  dia2000@gmail.com dia2000@gmail.com  on 

Hello, Our project is a LEED NC v2009. Due to a heavy rain season, it happened that some leakage lead to a partial grow of mold in some ceiling areas which are made from gypsum boards.

1
Sun Aug 27, 2017, 12:10 am

Adsorption Heat Pump

Homes-v4 EAc10:Space heating and cooling equipment
posted by  FABIO VIERO  on 

Hello everyone, in case of Gas Adsorption Heat Pump, which is the reference system we should consider for checking credit compliance? Thanks.

1
Tue May 9, 2017, 4:40 pm

1-floor renovation in an 2009 EBOM Certified Building

EBOM-2009 EAp2:Minimum Energy Efficiency Performance
posted by  John Krutko  on 

I am proposing on a project in which the scope is the renovation of a single floor of a 10 story building that is currently LEED 2009 EBOM certified.

1
Wed Apr 12, 2017, 8:28 pm

Energy Modelling - Australia

NC-v4 EAp2:Minimum energy performance
posted by  Quentin Jackson  on 

We have a Green Building Council in Australia that has a very advanced energy simulation methodology that achieves the same outcomes as the ASHRAE 90.1 process outlined in LEED.

1
Thu Apr 13, 2017, 2:56 pm

>10% exemption possible?

EBOM-2009 MPR2:Must be a complete, permanent building or space
posted by  Rasita Masalskyte  on 

Hello, Has anyone heard of possibility to exclude >10% of building gross area that is under separate ownership and management? In our case such space makes 14%.

0

Project size extended in the middle of construction

NC-v4 MPR3:Must comply with project size requirements
posted by  wachira sosaeng  on 

My project registered for LEED 2009, mixed use building with 2 towers on the same podium.

1
Tue May 30, 2017, 5:12 pm

Process Water

Retail-NC-v2009 WEp1:Water use reduction
posted by  Donald Green  on 

We have a project where there are a couple pieces of equipment that may be considered Process Water: a mobile pressure washer and a parts washer.