Topic

Option 1: Full Flush-out Before Occupancy- Is there a Min. CF?

CI-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Michelle Bracewell-Musson on Aug 4, 2011, 10:50 am

With Option 1, Path 1, we are expected to flush-out 14,000 cf/sf of outdoor air at 60 degrees temp. and 60% humidity min. Is there a minimum ventilation rate as with Path 2 which is 0.30 cf/min...

Last reply: Dylan Connelly, Sep 22, 2011, 11:37 am

Phased Occupancy and IAQ Testing

CI-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Melissa Wrolstad on Feb 22, 2011, 5:11 pm

I have a CI project with 4 floors and phased occupancy. Two floors will be occupied while two are still under construction. Is it possible to split...

Last reply: Susann Geithner, Feb 24, 2011, 9:53 am

Staged Move in and Natural Ventilation

CI-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Sam Keehn on Feb 9, 2011, 6:26 am

We are working on an office fit (3,800ft2) made up of basically 2 rooms. There have been some delays and the owner wants to move into one of the rooms while they finish the other. Provisions...

Last reply: Susann Geithner, Feb 10, 2011, 12:06 pm

International standards for Option 2, indoor air monitoring?

CI-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Reinhard Oppl on Jan 7, 2011, 2:14 pm

EQ credit 3.2, option 2, references to:
EPA Compendium of Methods for the Determination of Air Pollutants in Indoor Air.
Would any international standards be accepted as equivalent,...

Last reply: Tristan Roberts, Jan 9, 2011, 11:32 pm

Mechanical floors

CI-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Billy Ng on Nov 26, 2010, 10:29 am

I have a mechanical floor that is boxed in with no windows. this floor is just...

Last reply: Scott DeGaro, Nov 26, 2010, 11:57 am

Areas of question

CI-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Elizabeth Repin on Jan 22, 2010, 6:20 pm

We have a food distribution warehouse. Would the 82,000 sq foot freezer need...

Last reply: Shannon Gray , Apr 21, 2010, 4:32 pm

Flush monitoring requirements

CI-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Mary Davidge on Jan 20, 2010, 10:50 am

We have a project with two types of spaces, one is a naturally ventilated warehouse and the other is office with package units. At a local ashrae meeting the speaker stated that to achieve the...

Last reply: Tristan Roberts, Jan 20, 2010, 8:02 pm