Topic | Recent |
---|---|
Rainwater HarvestingNC-2009 SSc6.2: Stormwater design - quality controlposted by Udana Ratnayake on Jan 19, 2012, 5:25 am
Our project is harvesting and reusing rainwater for flushing. rainwater that falls on the roof is collected in a 10cubic meter sump. during a heavy rain the sump is allowed to over flow and the... Last reply: Amy Rider, Feb 22, 2012, 5:33 pm |
|
Landscape Over Underground Parking GarageNC-2009 SSc5.1: Site development - protect or restore habitatposted by Omer Moltay on Dec 7, 2011, 12:25 pm
In one project we are working on with multiple buildings sharing hardscape pedestrian plaza areas located on a common parking garage base, landscaping will be installed above the parking garage... Last reply: Devon Bertram, Feb 22, 2012, 2:55 pm |
|
Troubles filling the templateCS-2009 WEp1: Water Use Reductionposted by Stéphane Paris on Feb 22, 2012, 7:43 am
Hi, I'm working on a urban office building and have some troubles filling the template: - We will have automatic sensor for lavatories: how can I take it in consideration?... Last reply: Stéphane Paris, Feb 22, 2012, 12:21 pm |
|
Related to 62Mz CalcEBOM-2009 IEQp1: Minimum indoor air quality performanceposted by Dorilee Torres on Feb 17, 2012, 9:20 pm
On the requirements of this prerequisite it says " Each air-handler must be measured; sampling or grouping of air-handlers is prohibited"; If I have three... Last reply: Ben Stanley, Feb 22, 2012, 11:51 am |
|
ID Credits 5 pointsCS-2009 IDc1: Innovation in Designposted by Mike D on Feb 22, 2012, 9:08 am
Can the 3 paths be used in combination in order to achieve 5 points? I was wondering if it is possible to achieve 3 points under exemplary performance and then attempt 1 point for a pilot... Last reply: Tristan Roberts, Feb 22, 2012, 11:48 am |
|
Hotel occupancy rate and a/c energy consumptionNC-2009 EAp2: Minimum Energy Performanceposted by Orlin Velinov, PE on Feb 21, 2012, 11:55 pm
We have a hotel project with VRF systems serving the guest rooms. I am struggling with coming up with a way to simulate less than 100% occupancy rate in the hotel guest rooms. I am using HAP and... Last reply: Marcus Sheffer, Feb 22, 2012, 11:29 am |
|
Existing System with New Chiller PlantNC-2009 EAp2: Minimum Energy Performanceposted by Ante Vulin on Feb 22, 2012, 10:46 am
Our project is an existing 36,000 sf museum with a planned 18,000 sf addition. The existing portion is served by a dual-duct HVAC system with a boiler and chiller plant. The boilers and chillers... Last reply: Marcus Sheffer, Feb 22, 2012, 11:18 am |
|
6.2 90% Rainfall Trtmnt vs. Drainage Boundaryvs. Leed BoundaryCS-2009 SSc6.2: Stormwater design - quality controlposted by Dan Wise on Feb 22, 2012, 8:00 am
Does anyone know if Drainage Areas tributary to Treatment BMPs used to atain the 90% rainafall treatment and 80%... Last reply: Tristan Roberts, Feb 22, 2012, 11:18 am |
|
Auditors & ConsistencyEBOM-2009 IEQc3.2: Green cleaning - custodial effectiveness assessmentposted by Alexis Thompson on Feb 1, 2012, 11:05 am
Hello LEEDUser! I am working on a rather large building in NYC (2 million SF). They want to conduct an audit for IEQc3.2 but we are concerned about consistency. Here's why: 1) the building is... Last reply: Alexis Thompson, Feb 22, 2012, 11:11 am |
|
Occupancy Fitness CenterCS-2009 WEp1: Water Use Reductionposted by Ralf Lehmann on Feb 13, 2012, 11:05 am
Has anyone of experience in including a fitness center m to an office building. Last reply: Tristan Roberts, Feb 22, 2012, 8:49 am |