NC-v4 EAp2:Minimum energy performanceposted by Todd Tewksbury on
When modeling district cooling and heating systems using Option 1, Path 1: ASHRAE 90.1-2010 Appendix G, the LEED Reference Guide instructs the following: "If tariffs or rates are not available from
If all products in one category comply with the VOC emissions evaluation do we need to list the cost or surface area?
NC-v4 EQc2:Low-emitting materialsposted by Summer Gorder on
We are having a tough time getting the costs from our subs. The subs says that the cost is bundled with other material and they can't break it up.
Project Manager Job Opening at Sustainable Design Consulting's (SDC's) Washington, DC Office
posted by Sandra Leibowitz on
Sustainable Design Consulting, LLC (SDC) has immediate need for a high-performing, team-oriented Project Manager in our Washington, DC office to join our award-winning sustainability consultin
What suggestions are there for the case of moisture damage from rain?
NC-v4 EQc3:Construction indoor air quality management planposted by Karen Shilo on
Is it possible to utilize heating systems during new construction in order to dry out some moisture damage from rain prior to construction completion?
Air Sampling High Rises for Recertification
EBOM-v4.1 EAp2:Fundamental Refrigerant Managementposted by Karen Shilo on
What is the best way to air sample in the most efficient and cost effective way for a residential high rise for recertification?
LEED v4.1 If all products in one category comply with the VOC emissions evaluation do we need to list the cost or surface area?
NC-v4 EQc2:Low-emitting materialsposted by Summer Gorder on
We are having a tough time getting the costs from our subs. The subs says that the cost is bundled with other material and they can't break it up.
Daylight Study - Approach for partial wall coverings / multiple materials
CI-v4.1 EQc7:Daylightposted by Yarden Harari on
Hi All,
Has anyone come across a project that has multiple treatments on a wall (like an acoustic band), or multiple flooring finishes that are similar in shade / reflectance values?
Low Construction Waste Diversion Rate
NC-v4 MRp2:Construction and demolition waste management planningposted by Jason Cocek on
I have a project located in an area without access to good construction waste recycling services and the best option is to haul waste more than two hours away from the site.
"external" process energy for airports - jet bridges, ground power units, andpreconditioned air units
NC-v4 EAp2:Minimum energy performanceposted by Moses Chong on
Hello,