CS-2009 IEQc5:Indoor Chemical and Pollutant Source Controlposted by José Solis on
1) In the C&S 2009 requirements for IEQc5, there is a statement that says "Core & Shell projects that do not have entryway systems cannot achieve this credit." What exactly does that mean?
LEED project boundary and Data Centers
NC-2009 EAp2:Minimum Energy Performanceposted by Bethany Beers on
Hello, We have a new construction office building project in which a data center/computer room occupies about 10% of the area, but probably 95% of the load/energy.
Site visitors vs. FTE's
EBOM-2009 SSc4:Alternative Commuting Transportationposted by Kimberly Hosken on
In v2009 we are required to survey only the regular occupants and not the visitors regardless of how many visitors there are correct?
Regular Bus Service to Light Rail Station
CS-2009 SSc4.1:Alternative Transportation—Public Transportation Accessposted by Deborah Lucking on
I can guess the answer to my question, but am hopeful to be proved wrong: our project is within the 1/4 walking distance to a bus stop with a single service.
Waste Stream Audit
EBOM-v4 MRp1:Ongoing purchasing and waste policyposted by Trevor Anderson on
Under LEED v4, is the waste audit requirement the same for projects achieving initial certification and recertification, or do recertifying projects need to conduct one waste audit for each year of
Purpose behind the 60% RH parameter?
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Landry Watson on
The reference guide is clear that 14,000 CFM of OA per SF (that is >60deg and
Path 2 Flushout
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Amy Harmon on
Our project went with Path 2 Post-occupancy flush out. All AHUs required 2-4 days of flush out before occupancy could occur and about 24 days post occupancy.
Data Center Modeling - LEED CS version 2009
CS-2009 EAp2:Minimum Energy Performanceposted by Anurag Joshi on
Dear fellow modelers, I have a query regarding modeling and saving percentage calculation for datacenter buildings for LEED CS -2009.
EAc3 - Enhanced Commissioning, LEED v2009
NC-2009 EAc3:Enhanced Commissioningposted by Jared Reed on
Our project is pursuing EAc3 - Enhanced Commissioning. The reference manual states that the CxA performing the enhanced commissioning must also perform the fundamental commissioning.
Timeline to File an Appeal
posted by Jason Moody on
Our project was denied credit due to a failed pre-requisite during the final review. The client once us to file an appeal to address the pre-requisite.