Post a question or comment
Location Filters
Filter by location
Forum
Topic
Replies
Recent
2
Default Avatar
senior sustainable design consultant
Kaer Pte Ltd
LEEDuser Basic Member
2 thumbs up
Mon May 18, 2015, 1:20 pm

Fuel types of process energy

NC-2009 EAp2:Minimum Energy Performance
posted by  Jatuwat Varodompun  on 

We have a new plant using NGV as a fuel to fry potato chip in Thailand.

6
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Sat May 9, 2015, 1:23 am

Equipment Capacities for only one building pursue LEED

NC-2009 EAp2:Minimum Energy Performance
posted by  Indochine Engineering VN  on 

Hi, I have a District energy system (chillers, boilers, cooling towers, pumps) serves 3 buildings but only 1 pursues LEED, so my project doesn't use total capacities of those equipments.

5
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu May 7, 2015, 4:15 pm

Hi all,

NC-2009 EAp2:Minimum Energy Performance
posted by  Visu Boj  on 

I am working on a certification for a factory having less than 5 percent conditioned area. My process load is also high upto 75 percent.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Fri Apr 17, 2015, 5:03 am

Categorizing a LEED project

LEED Rating System Selection
posted by  Adi Negara, LEED AP BD+C  on 

Hello all, I have a difficulty in determining the appropriate LEED rating system for a project, and I hope that you all can tell me what rating system is best suited to the project: The project ow

2
Thu Apr 2, 2015, 2:48 pm

Process Load of a factory applying LEED CS

CS-2009 EAp2:Minimum Energy Performance
posted by  Jatuwat Varodompun  on 

I have a factory to be built for rent. Thus, this project goes for CS since we only build the shell.

3
Tue Mar 31, 2015, 3:32 pm

Daylight dimming with manual electric curtain

NC-2009 EAp2:Minimum Energy Performance
posted by  Jatuwat Varodompun  on 

My project has a dayligh dimming system and alos the curtain of each window. The reviewer ask me to add the effect of how this curtain will be modeled.

3
Tue Mar 31, 2015, 2:25 pm

Air Curtain in conditioned space

NC-2009 EAp2:Minimum Energy Performance
posted by  Jatuwat Varodompun  on 

How should we model the air curtain at the building entrance? Should we model as process load for both baseline and proposed?

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Mar 31, 2015, 1:20 am

Baseline HVAC Model System-8 VAV PFP Boxes with Outdoor Air Unit

NC-2009 EAp2:Minimum Energy Performance
posted by  Ivan Priatman  on 

Dear LEED, We are designing a medical office with VRF system, to fulfill iaq requirements we add independent outdoor air unit comprises of supply and exhaust fans on each zone.

9
Senior Designer
PT. Archimetric
LEEDuser Basic Member
4 thumbs up
Fri Mar 27, 2015, 10:02 am

Minimum Ventilation rates for Production area

NC-2009 IEQp1:Minimum IAQ Performance
posted by  sriram tetali  on 

Hi all Can u suggest the Ventilation rates for the Production / manufacturing areas for a Pharmaceutical clients because ASHRAE doesn't mention any for the Production in the Table 6-1

3
Manager -Sustainability Services
M W Group
LEEDuser Basic Member
1 thumbs up
Fri Mar 27, 2015, 7:01 am