Epoxy Flooring with ZERO VOC
NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systemsposted by Susan Morris on
I have a project with a large area of Epoxy Flooring, this epoxy contains 0% V.O.C.'s does it count as an inert material; or is testing required? Thank you
Reviewr's Comment is requesting labor and delivery
CI-2009 MRc4:Recycled Contentposted by Sarah Thompson on
In all my 40 LEED projects I have never included labor and delivery to a material's cost total.
Duct Sealant
NC-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealantsposted by Yaneth Galindo on
I used a duct sealant with VOC = 49 g/l and I am not sure if it complies with IEQ credit 4.1, because I do not know in which category it falls in the table.
Warehouse Office
EBOM-2009 IEQc3.5:Green Cleaning—Indoor Chemical and Pollutant Source Controlposted by Saul Pichardo, AIA on
My project has a 6,500sf office space serving a 207,000sf warehouse/distribution center (213,500sf total area).
Laboratory 90.1 Modeling
NC-2009 EAc1:Optimize Energy Performanceposted by Victoria Watson on
Hi, I am modeling a laboratory which has a small area of office space for LEED and wanted to check a couple of approaches: 1) The engineers have informed me that the lab has to be a once through sy
G3.1.10 (d) "Heating only System"
NC-2009 EAp2:Minimum Energy Performanceposted by Anil Bhari on
Based upon G3.1.10 (d) “Where no cooling system exists or no cooling system has been specified, the cooling system shall be identical to the system modeled in the baseline building” Does this mean
Final M&V Report
NC-2009 EAc5:Measurement and Verificationposted by Valerie Walsh on
We would like to know if the project can obtain its LEED certification prior to submitting the Final M&V Report, which is dependent upon 1 year of post-occupancy energy use data.
Unrenovated gross square footage
NC-2009 PIf2:Project Summary Detailsposted by Joseph Greene on
Our project is an addition to an existing building.
Baseline Return/Relief Fan Power
NC-2009 EAp2:Minimum Energy Performanceposted by Haojie Wang on
90.1 AppG G3.1.2.8 says the return/relief fan should be sized for max (SA-OA, 90%*SA) [cfm]. But in table 1.4. the allowable fan power is only based on the supply fan power.
LEED Certified C&D sites
NC-2009 MRc2:Construction Waste Managementposted by Frances Stark on
Is there a comprehensive directory of all the LEED certified recycling sites by state (or otherwise categorized)? I would love to see it.