Purpose behind the 60% RH parameter?
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Landry Watson on
The reference guide is clear that 14,000 CFM of OA per SF (that is >60deg and
Path 2 Flushout
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Amy Harmon on
Our project went with Path 2 Post-occupancy flush out. All AHUs required 2-4 days of flush out before occupancy could occur and about 24 days post occupancy.
Data Center Modeling - LEED CS version 2009
CS-2009 EAp2:Minimum Energy Performanceposted by Anurag Joshi on
Dear fellow modelers, I have a query regarding modeling and saving percentage calculation for datacenter buildings for LEED CS -2009.
Alternate Transportation: SSc4.3 and SSc4.4
NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehiclesposted by Greg Snow on
Hi Everyone, I am filling out the LEED letter template for SSc4.3 and SSc4.4 and don't know which path/option I should check.
EAc3 - Enhanced Commissioning, LEED v2009
NC-2009 EAc3:Enhanced Commissioningposted by Jared Reed on
Our project is pursuing EAc3 - Enhanced Commissioning. The reference manual states that the CxA performing the enhanced commissioning must also perform the fundamental commissioning.
Timeline to File an Appeal
posted by Jason Moody on
Our project was denied credit due to a failed pre-requisite during the final review. The client once us to file an appeal to address the pre-requisite.
Exemplary Performance?
CS-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealantsposted by José Solis on
The BD+C Reference manual states: "This credit is not eligible for exemplary performance under the Innovation in Design section." However, a response from Tristan Roberts on June 4, 2010 states th
Room Input Report
NC-2009 IEQc7.1:Thermal Comfort—Designposted by Bill Friedl on
I had a comment on a LEED review in IEQc7.1 to provide a summary table which lists the heating and cooling design parameters used for each space type and the Room Input Reports for each space type.
Option 1 Path 2 Temperature and Humidty Requirements
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Amy Harmon on
Path 1 indicates flush-out needs to be accomplished with 14,000 cu ft. of OA per sq. ft. of floor area while maintaining an internal temperature of at least 60 deg F and no more than 60% RH.
3 LEED projects sitting on a parking & retail layer cake
NC-2009 MRc4:Recycled Contentposted by Susan Di Giulio on
Hi, We have a campus master site occupying a city block. There are 7 podium floors with a hotel, condo towers and retail sprouting from them that are parsed into 3 separate LEED projects.