Group projects w/ DES / central plants

CS-2009 EAp2:Minimum Energy Performance
posted by  Stacey Olson  on 

This is with regard to an open air shopping plaza, which is registered as a group project with 7 structures. We received guidance to follow the “Treatment of District or Campus Thermal Energy in

1
Fri Aug 19, 2016, 4:57 pm

Fair Housing Act

Pilot-Credits PC34:Design for Adaptability
posted by  Kenneth O'Brien  on 

Why don't you just list the requirements for Fair Housing? The vague language of the list in the requirements is confusing.

0

Achieving Same Pilot Credit Twice?

Pilot-Credits IPpc81:Green training for contractors, trades, operators and service workers
posted by  Patty Lloyd  on 

Is it acceptable to attempt the same pilot credit on more than one project? For instance, I achieved PC81 on one project. I was wondering if it is acceptable to attempt it on another project?

1
Thu Feb 16, 2017, 1:22 am

Spray Foam Insulation

NC-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealants
posted by  Claire DeCamp  on 

I recently had a project manager approach me concerning spray foam insulation that has been specified on a project.

1
Wed Jul 22, 2015, 2:52 am

Preferred Parking

Retail-NC-v2009 SSc4:Alternative transportation
posted by  Kevin Flynn  on 

The LEED NC-Retail v2009 credit 4.3 and 4.4 to provide preferred parking for LEV/FE vehicles and Carpools appears to require that the project identify employee parking separate from customer parkin

1
Tue Aug 15, 2017, 9:01 pm

Flush out by AHU volume or Floor volume?

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Aru Sau  on 

In this project, there are three floors ( with multiple rooms with interior walls with doors) with multiple AHUs serving from 100% OA intake to 20% OA intake.

0

MRc4 Recycled content

CI-2009 MRc4:Recycled Content
posted by  Lorissa Kimm  on 

How does one count the recycled content of fabrics used in furnishings? Do you have to separate out the cost of the fabric relative to the cost of the chair?

1
Sat Oct 4, 2014, 6:27 pm

cabinet millwork

NC-2009 MRc7:Certified Wood
posted by  Karl Heitman  on 

We are installing plastic laminate millwork with particle board core which is not FSC certified. Does the cabinet costs need to be counted towards the total wood used in the project?

1
Wed Apr 6, 2016, 6:49 pm

Hotel Occupancy

NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  jupiter luner  on 

I've determined the occupancy for a hotel project we are working on based upon LEED interpretation 2706606.

1
Thu May 11, 2017, 4:48 pm

Option 4 - Transit Services Referenced

ND-v2009 NPDc8:Transportation demand management
posted by  Sara Zoumbaris  on 

For this credit under Option 4, there is a requirement to include additional spaces if our project has more than 100 dwelling units/ employees and has a minimum transit service of 60 daily weekday

1