Option 2: Is there an alternate compliance method being launced under LEEDv4.1
NC-v4 SSc2:Site development - protect or restore habitatposted by Stacey Olson on
It appears under LEEDv4.1 O+M, this credit was removed.
We have a site that is 19.1 acres, which equates to a cost of $332,798.40 at $0.40 / sf - a substantial cost for 1 point.
No issues
Pilot-Credits EApc111:Alternative Performance Rating Methodposted by Maureen Mahle on
I haven't found any major issue for this credit using this PC.
Lighting Power Allowance in Landmarked Building
CI-v4 EAp2:Minimum energy performanceposted by Nita Christopher on
We are attempting to certify a small tenant fit out (7,000sf) in a recently awarded LEED v4 EBOM Gold building with Landmark status.
LEED boundary - urban infill project - LEED V4 C&S
CS-v4 MPR2:Must use reasonable LEED boundariesposted by Thomas Gibbons on
Hi folks,
Carpet Tile as an Entryway System
NC-v4 EQc1:Enhanced indoor air quality strategiesposted by James Keohane on
The Reference Guide for EQc1, Option 1- Entryway Systems describes entryway system in part ..…...
LEED User Concrete Tracking Form
NC-2009 MRc4:Recycled contentposted by Melanie Blacklock on
Trying to use the LEED User Concrete Tracking Form for the first time to track fly ash. My question concerns Item I: Distances from both harvesting AND manufacturing point to project site (miles).
How to calculated for hybrid urinals
CI-2009 WEc1:Water use reductionposted by Susan Di Giulio on
Sloan has a new "hybrid" urinal that is basically waterless but does a pre-programmed, 1 gallon system flush every 72 hours. This solves a lot of maintenance and odor problems.
Finding an auditor
EBOM-2009 IEQc3.2: Green cleaning - custodial effectiveness assessmentposted by Joanne Sawatzky on
Hi,
Do any of you have a recommendation on where to find a 3rd-party APPA auditor? This is for a project in BC, Canada. Thanks in advance!
SJ
Vertical Expansion v. Horizontal Expansion
Healthcare-v4 MRc8:Design for flexibilityposted by Mary Couch on
Hello! I'm working on a project and we can only achieve Modular/Movable Casework, Vertical Expansion and Horizontal Expansion.
Heat Island Reduction: Parking under Cover
Healthcare-v4 SSc5:Heat island reductionposted by Mary Couch on
I am on a project currently where we are pursuing option one of the Heat Island credit, we are curious as to whether we are able to pursue option B as well.