Enchanced Cx - District/Campus System Guidance - Floor Area trigger

NC-v4 EAc1:Enhanced commissioning
posted by     on 

One of the triggers of the upstream equipment Cx requirements for EAc1 is that the "project building's gross floor area is greater than 50,000 square feet." Does this 50,000 GSF trigger refer to th

0

Option 4 - whole building life cycle assessment

NC-v4 MRc1:Building life-cycle impact reduction
posted by  Chloe Naese  on 

Hello, could this credit be pursued for a major renovation of a building, or does it only apply to new construction? Thanks!

3
Senior Sustainability Consultant
Steven Winter Associates
LEEDuser Premium Member
10 thumbs up
Tue Oct 2, 2018, 1:11 pm

Shuttle between building and secured site entrances

NC-2009 SSc4.1:Alternative transportation - public transportation access
posted by  J Douglas Dietrich  on 

Distance from LEED building to public transit stops is too far to meet requirements, however distance from the guardhouse gate controlling access to the secured site on which the LEED building is l

4
Senior Principal | Director of Sustainability Integration
SmithGroup
LEEDuser Expert
43 thumbs up
Fri Sep 28, 2018, 10:48 am

SSc6

EBOM-v4 SSc6:Site improvement plan
posted by  Yaretzy Charo  on 

What does it mean by documentation of existing site conditions? 

3
Thu Sep 27, 2018, 9:08 pm

Asphalt with Recycled content (RAP)

NC-2009 MRc4:Recycled content
posted by  Rick Alfandre  on 

Has anyone used Ashpalt with recycled asphalt?  Reading the forums, it seems it will apply, but I'm having trouble determining what possible percentage of recycled content (pre or post consume

2
Wed Sep 26, 2018, 7:27 pm

Small Project BoD

CI-2009 EAp1:Fundamental commissioning of building energy systems
posted by  Claire Cowling  on 

I picked up a project in my firm after the first review was compelted. It seems that a BoD was never created for this project, as it is very small and the CxA was hired late.

0

HPD v2.1 - Statement about Special Conditions when "No" is indicated for Characterized, Screened, or Identified

NC-v4 MRc4:Building product disclosure and optimization - material ingredients
posted by  Ashley Hu  on 

I’m currently reviewing a HPD v2.1 for LEED v4 Building Product Disclosure and Optimization – Material Ingredient Option 1.

5
Thu Sep 20, 2018, 2:57 pm

Regional material distance calculation method

CS-v4 MRc3:Building product disclosure and optimization - sourcing of raw materials
posted by  Lawrence Rennell  on 

According to LEED 2009, there were alternate distance calculations available that applied to products shipped by rail or ship.

0