Indoor Air Quality Procedure

NC-v4 EQp1:Minimum indoor air quality performance
posted by  James Keohane  on 

I understand that the credit language requires the use of the Ventilation Rate Procedure(VRP) from ASHRAE 62.1-2010.

2
Mon Aug 10, 2020, 10:04 pm

How many units needed for air testing.

Mid-Rise-v4 EQc2:Contaminant control
posted by  Jillian Hansen  on 

I am working on a project that has one ventilation system and each of the 6 floors are less than 25,000SF.

0

Independent Living Units NOT Included??

NC-v4 EQc5:Thermal comfort
posted by  James Keohane  on 

Project Information:  A LEED V4 New Construction project consisting of a three story clubhouse with Independent Living units on the upper four floors.  The Cluhouse elements account for 6

0

LEED Boundary with Main Building, Parking Garage & Parksmart

NC-v4 MPR2:Must use reasonable LEED boundaries
posted by  Ralph Bicknese  on 

We have a new 609,000 sf building seeking LEED BD+C v4 certification. A new 1800 space parking garage will be built design-build as part of the project but by separate designer, same CM.

3
Principal
Hellmuth & Bicknese Architects
LEEDuser Premium Member
20 thumbs up
Thu Aug 6, 2020, 5:44 pm

Lead-free paint

Healthcare-v4 MRc6:PBT source reduction - lead, cadmium and copper
posted by  Mark Meaders  on 

I was looking to see if there is a threshold that states the amount of lead in paint that is considered lead-free (something along the lines of what is stated for pipes or flux).

1
Mon Oct 12, 2020, 1:16 pm

Language for signs?

NC-v4.1 EQp2:Environmental Tobacco Smoke Control
posted by  emily reese moody  on 

Has anyone used the updated v4.1 version of this and has a good way to phrase the signage? Seems even more awkward than the previous needs.

7
Wed Aug 5, 2020, 6:59 pm

25% Threshold?

NC-v4.1 MRc3:Sourcing of Raw Materials
posted by  Douglas Flandro  on 

In the LEEDUser's take on this credit there is a sentence that says, "There is no minimum threshold of recycled content

1
Mon Aug 3, 2020, 5:18 pm

Rooftop Pool

NC-v4 SSc5:Heat island reduction
posted by  Danielle Waters  on 

If a residential project with a rooftop pool wants to pursue SSc5-Option 1, but how does the pool full of water impact the calculations? Is the pool sq.ft.

1
Fri Aug 14, 2020, 4:54 am

EQpc117: Quality views in nonregularly occupied spaces.

NC-v4 INc1:Innovation
posted by  Marie Bizzak  on 

We are working on a project that is already getting an exemplary credit for quality views. Is it possible to get this exemplary credit in addition to the pilot credit?

3
Senior Project Manager
Zinner Consultants
LEEDuser Basic Member
110 thumbs up
Thu Jul 30, 2020, 9:54 pm