Commissioning building areas

CS-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  gabriel Morales  on 

We have a process of commissioning CS 2009 , and we have a question: In the reference guide mentioned that 50,000 SF smaller projects the contractor could be the CxA , however the area of ​​50,00

2
Chief Environmental Officer
Alpenglow Advisory
LEEDuser Basic Member
44 thumbs up
Wed Feb 24, 2016, 5:09 pm

Linen Area

Healthcare-v2009 IEQp1:Minimum indoor air quality performance
posted by  Gabriela Crespo  on 

Hi! I have a question regarding the ventilation requirement for the Linen Area, according to the Space Matrix file, there needs to be Outdoor air for this space.

2
LEED-AP BD+C
GREENSQUARE
LEEDuser Expert
261 thumbs up
Mon Feb 15, 2016, 3:38 pm

2 office floors on a 20 stories building

EBOM-v4 MPR2:Must use reasonable LEED boundaries
posted by  Michael E. Edmonds-Bauer  on 

Hello, We have a cliente that is interested in pursuing LEED for his brand new offices.

4
Tue Jan 5, 2016, 7:23 pm

Naturally Ventilated, Mechanically Cooled space

NC-2009 IEQc7.1:Thermal Comfort—Design
posted by  Gabriela Crespo  on 

In ASHRAE 55, Section 5.3 Optional Method for Naturally Conditioned, it mentions that "There must be no mechanical cooling system for the space".

2
Tue Dec 1, 2015, 4:38 pm

Balancing Devices to meet ASHRAE 90.1 Mandatory Requirements

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Jorge Torres-Coto  on 

We have a project that is an industrial facility, it shares the CHW distribution piping between the comfort system and the process system. We are informing the CxTeam that it is required to have b

2
Director of Commissioning & Critical System
Edwards & Zuck
LEEDuser Basic Member
29 thumbs up
Thu Nov 19, 2015, 6:52 pm

Shared building electricity meter

EBOM-v4 EAp2:Minimum energy performance
posted by  LEED Pro Consultant  on 

We have a building which shares electricity meter with an adjacent building, only one building will be intended for certification, it is possible to identify the percentage of consumption in every

2
Senior Sustainability Manager
WSP - Built Ecology
LEEDuser Expert
188 thumbs up
Thu Jul 2, 2015, 8:39 pm

Reactivating construction with ESC Plan, no ESC Plan before

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  LEED Pro Consultant  on 

Hello! We have a project that started construction some time ago, and stopped 1 yr ago, leaving only the foundation. At this time, they were not considering LEED as an objective.

4
LEED Project Manager
SIDEworks
LEEDuser Basic Member
0 thumbs up
Tue Jun 16, 2015, 10:33 pm

Waste classified

NC-2009 MRc2:Construction Waste Management
posted by  Alicia Villanueva  on 

Construction waste will be separated onsite. It will be hauled (altogether in the same truck) to centers where workers clasify the waste and sell it to companys which take it to recycling plants.

2
Default Avatar
LEEDuser Expert
472 thumbs up
Sun May 31, 2015, 3:56 pm

FSC MIX

NC-2009 MRc7:Certified Wood
posted by  jorge calderon  on 

Hello! I´m documenting a floor that is FSC MIX, does it means that I can count it as 100%? I´m not sure because the label only says MIX, not FSC Mixed Credit, neither FSC Mixed (NN)%. Thanks in

7
Default Avatar
Manager, Sustainability and Technical Marketing
Masonite Architectural
LEEDuser Basic Member
57 thumbs up
Wed May 27, 2015, 2:30 pm

Systems manual

CS-2009 EAc3:Enhanced Commissioning
posted by  Michael E. Edmonds-Bauer  on 

We are done with our commissioning process and almost ready to submit for preliminary construction review, however the systems manual (Upload EAc3-1) is develop in Spanish language since it is the

4
Tue Mar 24, 2015, 10:58 pm