Living/Green Walls

CS-v4 SSc3:Open space
posted by  Ward Miller  on 

Has anyone tried using the area of a green wall to achieve the 25% vegetated space portion of this open space requirement?

2
Sustainable Design Consulting
LEEDuser Basic Member
20 thumbs up
Wed Apr 19, 2017, 8:01 pm

Local voluntary cleanup program - definition

NC-2009 SSc3:Brownfield Redevelopment
posted by  Anna Korinkova  on 

Under Option 1 of the credit, we can pursue EITHER the ASTM E1903-97 Phase II Environmental Site Assessment OR the 'local voluntary cleanup program'.

3
Mon Mar 13, 2017, 4:52 pm

ASHRAE 90.1-2007, 6.5.3.1.1,exception b

NC-2009 EAp2:Minimum Energy Performance
posted by  Vassil Vassilev  on 

Greetings, According to ASHRAE 90.1-2007, 6.5.3.1.1,exception b, individual exhaust fans with motor nameplate kW of 0.75 kW or less could be excluded when estimating Fan system power limitation. Th

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon Feb 13, 2017, 6:02 am
2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Feb 7, 2017, 3:42 pm

Can a LEED AP ID+C v4 earn IOc2 EBOM 2009 ?

EBOM-2009 IOc2:LEED Accredited Professional
posted by  Izabela Kwiecinska  on 

Hi Everyone, I am working on LEED EBOM project that was registered in 2009 system. The same time I am preparing for my LEED AP exam (have chosen ID+C speciality).

2
Project Director
WSP USA
LEEDuser Basic Member
381 thumbs up
Fri Feb 3, 2017, 3:04 pm

Which ASHRAE & LEED should I base my simulation on?

NC-2009 EAp2:Minimum Energy Performance
posted by  Olaf Dybinski  on 

Hello, I have a problem with choosing a basis for my simulation. I have a building that was designed in 2015 and is about to be build.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Jan 12, 2017, 8:04 am

Fan Power and Fan Power Adjustment (FPA)

NC-2009 EAp2:Minimum Energy Performance
posted by  Vassil Vassilev  on 

Greetings, In the project we are modeling, the following issues are still not quite clear for us and we'd appreciate any advice on the matter. Baseline system is 8.

6
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Nov 8, 2016, 3:48 pm

Wood pellets as a Renewable energy source

NC-2009 EAc2:On-Site Renewable Energy
posted by  Vassil Vassilev  on 

We are at conceptual design stage for a new school building.

5
Wed Sep 28, 2016, 3:09 am

LCA Part A4 and A5 – Transport to site and Construction installa

NC-v4 MRc1:Building life-cycle impact reduction
posted by  Petr Vogel  on 

Dear all, I do have a lot of questions since this credit approach is brand new + the whole LCA analysis is definitely not yet wide spread on the market. Since A4+A5 is specified to be included in

15
Default Avatar
President
Athena Sustainable Materials Institute
LEEDuser Basic Member
6 thumbs up
Sun Sep 25, 2016, 8:53 am

Decorative blue light fixtures

CI-2009 EAc1.2:Optimize Energy Performance—Lighting Controls
posted by  Agnieszka Rylska  on 

In our office project there are daylight sensors within 15 feet of the windows which are connected to all lighting fixtures in daylit areas except for a few decorative fixtures on the ceiling (prov

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Fri Sep 9, 2016, 3:52 pm