Forum quick links
Equipment as per table 6.8.1.A 90.1-2007
NC-2009 EAp2:Minimum Energy Performanceposted by Vassil Vassilev on
Greetings, In the project we are modeling, there are air conditioners which are supposed to operate in cooling mode at OA temperature close to the design heating OA. In this table and also in othe
Parking spaces for trucks
NC-2009 SSc4.4:Alternative Transportation—Parking Capacityposted by Alicja Bieszyńska on
My project is a distribution center that serves number of loading trucks every day.
Sensors calibration during the performace period
EBOM-2009 EAc3.1:Performance Measurement—Building Automation Systemposted by Agnieszka Rylska on
Is it necessary to calibrate sensors during the performance period even if the manufacturer’s recommended interval didn't pass yet?
access to medical point and massage point
NC-2009 IDc1:Innovation in Designposted by Agnieszka Rylska on
We are considering options for innovation credits.
CO2 sensors in retail spaces
CS-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Agnieszka Rylska on
Should retail spaces in a shopping mall have CO2 sensors? Does anyone know if shops are treated as densely occupied spaces?
Certificates for hot district water?
EBOM-2009 EAc4:On-Site and Off-Site Renewable Energyposted by Izabela Kwiecinska on
Hello Everyone, We are preparing our Client to buy Green-e certified energy. We don't know if he has to buy also GOs or carbon offsets for district hot water that the building is supplied with.
LEED EBOM
Pilot-Credits EQpc78:Design for active occupantsposted by Lukas Urban on
Hi! Can we use this Pilot-Credit in a LEED EBOM project? Our staircase meets almost all the conditions. Thank you.
VRP Compliance Calculator
NC-2009 EAp2:Minimum Energy Performanceposted by Vassil Vassilev on
Greetings, Regarding VRP Compliance Calculator (IEQp1), there is a question on how to enter an AHU having the following characteristics: The AHU is a constant volume device; supplying to several
Baseline System 9 fan details
NC-2009 EAp2:Minimum Energy Performanceposted by Vassil Vassilev on
Greetings, We have zones in our project which are addressed to system 9 (heating only).
renovation of multiple non-contiguous parts of an office
CI-2009 MPR2:Must be a complete, permanent building or spaceposted by Agnieszka Rylska on
The owner has a certified office which is located on a few floors of a building. Now he's going to renovate a part of it. On one floor there will be a few non-contiguous parts renovated.