Does the main water meter count as 1 of the 2 required submeters?
Schools-NC-v4 WEc4:Water meteringposted by Kay Santangelo on
I'm working on a project where the plumbing engineer is providing a main water meter at the building entrance and one submeter at the hot water system.
District heating form sewage sludge combustion as renewable energy?
NC-v4.1 EAc5:Renewable Energyposted by J Schütz on
Dear all,
40% of the district heating one of our projects procures is generated from the combustion of sewage sludge and Biogenic waste.
Daily Journal Question
Pilot-Credits INpc136:Safety First: Re-Enter Your Workspaceposted by Marina Andrade on
For a LEED ID+C certification process could my client use a Daily Journal with questions already used in the operation of the office?
How to calculate Area with Direct Line of site without 90 degrees??
NC-v4 EQc8:Quality viewsposted by Elisaa Wu on
I am confused as to how to calculate the "Area with Direct Line of Sight to the Outdoors via Vision Glazing (sq ft)" on the excel calculator form.
Regeneration - Anthem!
posted by Mary Ann Lazarus on
Thanks to SERA especially David, Kira and Clark for an inspirational conversation with Paul Hawken about his latest book. I know I needed a positive perspective!
Survey period
EBOM-v4.1 LTp1:Transportation Performanceposted by LEED Pro Consultant on
Hi,
We are working on a project with an occupancy of 1,500 people. According to the reference guide, at least 250 surveys should be done to get a score.
Community Anchor Uses - do only commercial offices count?
NC-v4 LTc4:Surrounding density and diverse usesposted by Deborah Lucking on
Our project is next to a public agency building that employs more than 100 employees. Does this count?
Is there a reason why only commercial offices qualify?
Lighting Levels in Commercial Kitchens
NC-v4 EQc6:Interior lightingposted by Greg Romanczyk on
Is there an exclusion for commercial kitchens needing to meet the EQc6 mutli-occupant lighting levels? We are working on a hotel project, with a restaurant, where the kitchen has switches but
Demolition of existing building
NC-v4 MRc5:Construction and demolition waste managementposted by Erik Heck on
We have a project which will be built on the site of an existing building. Does the demolition of that existing building need to be included in the MRc5 waste diversion calculations?