smoke leakage test for duct

NC-2009 EAc3:Enhanced Commissioning
posted by  Abdulla Anwar  on 

Our MEP sub-contractor need to clarify if we can use an smoke capsule for duct leakage test? prior to air leakage test since the project specs is giving a small allowable 1% from basis of design?

3
Lead Design Architect | LEED Professional coordinator
Nesma & Partners
LEEDuser Basic Member
0 thumbs up
Mon Feb 27, 2017, 9:11 pm

District Energy Cx Guidance

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Candice Rogers  on 

Hello, We have a project that meets the requirements of District Energy Systems. There is one new piece of equipment and multiple existing that will serve the facility.

2
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Wed Feb 22, 2017, 6:08 pm

LEED Clarification for Filtration Credit Requirements

NC-2009 IEQc5:Indoor Chemical and Pollutant Source Control
posted by  Mary Kay  on 

We've heard that per a recent LEED clarification for filtration credit requirements, MERV 13 filtration is required on ALL outdoor air handling units, not just those serving regularly occupied spac

2
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Wed Feb 22, 2017, 5:49 pm

MR 2.2 Form Change

EBOM-2009 MRc2:Sustainable Purchasing—Durable Goods
posted by  Fred Smith  on 

I am confused as the the new form on LEED On Line vs what you are showing on LEED User. I am not sure what is needed to upload in regards to our purchasing and criteria for sustainability.

4
Wed Feb 22, 2017, 5:10 pm

Documented floor plans with occupancy scale

CI-2009 EAc1.2:Optimize Energy Performance—Lighting Controls
posted by  Edgar Arevalo  on 

Before I began uploading the floor plans showing the controls and lighting equipment on the LEED online template for EAc1.2, I noticed that the templates requests floor plans indicated which zones

2
Director - Green Building Advisory
Colliers International Ltd.
LEEDuser Basic Member
201 thumbs up
Wed Feb 22, 2017, 4:07 pm

owner/tenant contract

CS-2009 EAc6:Green Power
posted by  FABIO VIERO  on 

Hi all, we are working on a shell&core project that, once completed, will be a single tenant occupied buiding.

3
Head of Sustainability
Manens S.p.A.
LEEDuser Premium Member
16 thumbs up
Wed Feb 22, 2017, 2:28 pm

Rooms designed with no windows, but still part of ROA

NC-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Anna Korinkova  on 

Are there any areas that can be exempt from dayligting calculations, while still being part of ROA?

4
Tue Feb 21, 2017, 8:53 pm

advanced buildings doc

General forums
posted by  Tristan Roberts  on 

Joshua, not sure what to say... I can't find a copy either. It's not a resource we have referenced on this site, and I'm not familiar with it.

17
Tue Feb 21, 2017, 8:32 pm

Daylight Sample

NC-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Alex Barrera  on 

Hello, is there a filled out sample of the Daylight/Views calculator Spreadsheet anywhere? I'm using the prescriptive method to conduct the Daylight calcs.

2
Energy Program Specialist
PA DMVA
LEEDuser Expert
626 thumbs up
Tue Feb 21, 2017, 7:58 pm

CSRs

NC-v4 MRc3:Building product disclosure and optimization - sourcing of raw materials
posted by  Helene Lefkowitz  on 

Are CSRs required simply for manufacturer's (a blanket report that encompasses all products made by a particular manufacturer), or are CSRs required for each individual product?

3
Default Avatar
Director
ANCL
LEEDuser Basic Member
0 thumbs up
Tue Feb 21, 2017, 7:12 pm