Hiring CxA for Construction other than one hired during Design

NC-v4 EAc1:Enhanced commissioning
posted by  mohammad Hassan  on 

Can a different CxA for a project Construction Phase be hired other than the one hired during Design Phase ?

3
Sun Jun 11, 2017, 4:53 am

v4 SSc6 - Hardscape requires a minimum of 0.2 fc to be counted

General forums
posted by  Bill Swanson  on 

Been awhile since this thread has been used. This has come up on a project and we lost on appeal so I'm sharing this information with everyone. Any area being claimed in the wattage baseline calc

7
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Fri Jun 9, 2017, 6:58 pm

list of approved programs?

NC-v4 MRc4:Building product disclosure and optimization - material ingredients
posted by  emily reese moody  on 

I could have sworn I saw a link somewhere in LEEDUser to a list of approved programs to use for this credit (that also gets updated as USGBC adds more programs), but can't find it now. Did I imagin

2
Founder & Community Director
Metricorps
LEEDuser Expert
7780 thumbs up
Fri Jun 9, 2017, 5:40 am

CARB and ECO-Certified

General forums
posted by  Erika Duran  on 

I have a sub that just submitted documentation for Particle board that is "Third party certified (California ARB approve TPC-1) to comply with CCR 93120.2 (CARB Composite Wood ATCM).

11
Thu Jun 8, 2017, 8:15 pm

Pending Systems for Commissioning

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Shabari Shaily Gerber  on 

Hi We are currently busy with LEED documentation of a manufacturing facility that is under operation for a year now.

4
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Thu Jun 8, 2017, 6:53 am

Ground-Mounted Solar PV Arrays

NC-2009 SSc5.2:Site Development—Maximize Open Space
posted by  J Douglas Dietrich  on 

If there is an open space with (1) a ground-mounted solar PV array and (2) native plantings or adapted vegetation beneath the PV panels and around them so as not to block sunlight, would the area b

5
Default Avatar
AIA, LEED-AP, BD&C
Fox Architects
LEEDuser Basic Member
5 thumbs up
Wed Jun 7, 2017, 5:46 pm

BD+C New Construction - New Stadium

NC-v4 MPR2:Must use reasonable LEED boundaries
posted by  Quentin Jackson  on 

Hi all, I'm preparing to register a new project (new stadium) and would like to double check that it is a 'single building'.

2
Sustainable Design Leader
HKS, Inc.
LEEDuser Premium Member
40 thumbs up
Wed Jun 7, 2017, 5:41 pm

C&S 2009 Office bldg, hotel tenant impact

NC-2009 PIf3:Occupant and Usage Data
posted by  James Emery  on 

We have a 31 storey office tower under construction and slated for substantial in October 2017. It was designed and construction started without any confirmed tenants.

3
Principal
Iredale Architecture
LEEDuser Basic Member
0 thumbs up
Wed Jun 7, 2017, 5:06 pm

EPA New Version

NC-v4 SSp1:Construction activity pollution prevention
posted by  Jennifer Webb  on 

The EPA has issued the 2017 Construction General Permit (see web page https://www.epa.gov/npdes/stormwater-discharges-construction-activities-2017-cgp) that became effective on February 16, 2017.

2
Wed Jun 7, 2017, 4:35 pm

LEED methodology for calculating water use/efficiency baseline

NC-2009 WEp1:Water Use Reduction—20% Reduction
posted by  Kwame Emmanuel  on 

Greetings, I am currently researching the LEED methodology for calculating a water use/efficiency baseline for the housing sector. Any links or advice would be greatly appreciated. Regards.

5
Tue Jun 6, 2017, 8:40 pm