Forum quick links
ASHRAE 90.1-2007: Minimum Efficiency Requirements (Heat pump)
NC-2009 EAp2:Minimum Energy Performanceposted by Jorge Mato Rial on
Hello Everyone: I am working in an office building project located in Galicia (Spain). We are carrying out the selection process of the heat pump for the air conditioning of the building.
LEED v4 Requirements documentation
posted by nancy picard on
Hi, I've been searching for LEED v4 Canadian Construction Documents (01 35 21), but the update hasn't been performed yet.
dimension calculation methodology
CI-2009 IEQc8.2:Daylight and Views—Views for Seated Spacesposted by Noriko Nagazumi on
When we calculate "regulary occupied space" for EQc8.2, is it supposed to be inside of wall or "center on center" ?
HERS rating for 3-Stories multifamily building
ND-v2009 GIBp2:Minimum building energy efficiencyposted by Mugdha Mokashi on
For low-rise multifamily buildings is it possible to show compliance with this prerequisite by achieving a HERS index of less than 75?
Exterior lighting not yet designed
NC-2009 EAp2:Minimum Energy Performanceposted by Vassil Vassilev on
Greetings, The project we are modeling at the moment is supposed to have exterior lighting for the facades, some parking lots and some walkways. The exact LPD however is still to be calculated and
Existing constructions and non infiltration water tanks
ND-v2009 GIBc8:Rainwater managementposted by Noriko Nagazumi on
Hello. Two questions: Are existing constructions required to be part of the project stormwater management? The reference book wording refers to "management plan for the project".
Baseline Garage Ventilation
NC-2009 EAp2:Minimum Energy Performanceposted by Vassil Vassilev on
Greetings, In our project (registered as per LEEDv2009) there are several garage ventilations. According to ASHRAE 62.1-2007, the garage exhaust rate is to be sized to 0.75 cfm/ sq.ft.
Energy Rates for CHP used Project
NC-2009 EAp2:Minimum Energy Performanceposted by SAMY Chamy on
Dear All Our Project have CHP (2 CNG Generator 500Kw with VAM Chillier 100TR) what is rate we use for BASE Case and Design Case For Design case we use the Fuel(CNG) cost invested to run a Gener
Project with no off-street parking spaces
ND-Plan-v4 NPDc5:Reduced parking footprintposted by Noriko Nagazumi on
Hi, Our project has no off-street parking spaces.
Modeling Limitations to the Simulation Program
Data-Centers-NC-v4 EAp2:Minimum energy performanceposted by Vasileios Kalfountzos on
I am currently working on developing the baseline building for our Energy modelling and I'm stuck on the following point of Table G3.1 point 13. "If the simulation program cannot model a component