NC-v4 EAc1:Enhanced commissioningposted by Heather Holdridge on
I understand that there were not any requirements regarding TAB in LEED 2009 -- is this still true for v4? Just want to confirm that there are no issues with having the balancer contracted un
Flush-out of a Modular Building
NC-v4.1 EQc4:Indoor Air Quality Assessmentposted by Neil Rosen on
If I am fabricating the building off-site in modules and assembling those modules on-site, can I perform the flush-out in the factory?
Contractor's Commitment reporting template--in progress
posted by Candace Pearson on
Hello all,
UPS rooms for LEED
CS-v4 EAp2:Minimum energy performanceposted by Rajat Wadhwa on
Hi, I am working on a Data Center and I am confused if we should model UPS rooms for LEED and what schedule should I use since its a backup supply room incase the power goes .
Modeling UPS Room for Data Center
NC-2009 EAp2:Minimum Energy Performanceposted by Rajat Wadhwa on
Hi, I am working on a Data Center and I am confused if we should model UPS rooms for LEED and what schedule should I use since its a backup supply room incase the power goes .
UPS rooms for LEED
NC-2009 EAp2:Minimum Energy Performanceposted by Rajat Wadhwa on
Hi, I am working on a Data Center and I am confused if we should model UPS rooms for LEED and what schedule should I use since its a backup supply room incase the power goes .
No Cooling Tower
NC-v4.1 WEc3:Optimize Process Water Useposted by Azra on
Hello,
we are working on numerous projects which do not include a cooling tower nor evaporative condensers.
Optimize Process Water Use, Option 2 with ASHRAE 90.1 2010 model?
NC-v4.1 WEc3:Optimize Process Water Useposted by Deb Favaretto on
We are submitting a LEED v4 BD+C NC project with LEED v4.1 upgrades on a credit-by-credit basis. Minimum and Optimize Energy Performance have remained v4.
Multilevel lighting control
NC-v4.1 EQc6:Interior Lightingposted by Michael on
I have 10 lighting fixtures in an office space, and the architect is providing 3 on-off switches:
- switch 1, on-off 5 lightings (50% of lighting numbers)