Topic | Recent |
---|---|
Energy Star Portfolio ManagerEBOM-2009 EAc1: Optimize Energy Efficiency Performanceposted by Reynaldo Castro on May 10, 2010, 6:42 pm
I have a question in regards to the Energy Star Portfolio Manager. We are currently purchasing 30% offsite... Last reply: Jenny Carney, May 12, 2010, 10:35 am |
|
Calculating re-used building's contribution to MR 2NC-2009 MRc2: Construction Waste Managementposted by Alison Y Rivenburgh on May 6, 2010, 1:21 pm
According to the reference guide, "projects that... Last reply: Tristan Roberts, May 12, 2010, 5:00 am |
|
Separate Demolition Package from Construction PackageNC-2009 MRc2: Construction Waste Managementposted by Alison Y Rivenburgh on May 6, 2010, 1:37 pm
A large project with a building slated for demolition - the demo package is completely separate from the construction package, and will take place half/full year in advance of construction. The... Last reply: Tristan Roberts, May 12, 2010, 4:54 am |
|
Flush Out for Multi Family Residential ProjectEBOM-2009 IEQc1.5: Indoor air quality best management practices - indoor air quality management for facility additions and alterationsposted by Thomas Fisher on Apr 27, 2010, 1:18 pm
I am working on a LEED EB: O&M project and wondering if you could provide guidance as to whether the following would be an acceptable alternative compliance approach to achieving EQc1.5:... Last reply: David Posada, May 11, 2010, 7:12 pm |
|
Weekend Paint and Carpet?EBOM-2009 IEQc1.5: Indoor air quality best management practices - indoor air quality management for facility additions and alterationsposted by D. G. on May 10, 2010, 3:10 pm
I have a question about whether painting and carpet replacement in a tenant suite, taking place on the weekends, counts as a facility alteration. The definition cited in the Reference Guide is... Last reply: David Posada, May 11, 2010, 6:48 pm |
|
Grout for Concrete RepairNC-2009 IEQc4.2: Low-emitting materials - paints and coatingsposted by Omer Moltay on May 4, 2010, 9:54 am
Hello, Which category in... Last reply: Abena Darden, May 11, 2010, 1:33 pm |
|
Required Waste haulersEBOM-2009 MRp2: Solid Waste Management Policyposted by Janna Nash on May 8, 2010, 4:18 pm
Can you tell me if contracts with waste haulers are required? My project is a small office building located on a college campus. Currently the office personnel or college students carry all... Last reply: Tristan Roberts, May 11, 2010, 11:18 am |
|
Taxes and Other feesCI-2009 MRc7: Certified Woodposted by EMILY KANAREK on Apr 29, 2010, 11:18 am
Are taxes and transportation fees included in the product cost? I can't seem to find this anywhere! Thanks! Last reply: Tristan Roberts, May 10, 2010, 10:47 pm |
|
FSC Certified BambooCI-2009 MRc7: Certified Woodposted by Jerry Phelps on May 10, 2010, 5:37 pm
If our project is using bamboo, does that mean that our bamboo has to be... Last reply: Tristan Roberts, May 10, 2010, 10:43 pm |
|
Title 24 instead of ASHRAE in CI 2.0CI-2009 EAc1.1: Optimize energy performance - lighting powerposted by Janika McFeely on Apr 8, 2010, 5:50 pm
We received a comment back on a review of a CI 2.0 project requiring us to use the ASHRAE standard instead of Title 24 (as it states in the 2.0 reference guide). We would be ok under LEED CI 2009... Last reply: Dave Intner, May 10, 2010, 12:22 pm |