Req'd # of integrative design team (with owner) seems highPilot-Credits PC6: Integrative Project Planning & Designposted by Renee Shirey on Sep 30, 2010, 3:34 pm
I am all for regularly scheduled LEED/sustainability mtgs with the team, but to have that many (12!) and require the owner to be at each of them stops them from being beneficial working mtgs and... Last reply: Tammy George, Oct 19, 2010, 1:49 pm |
|
Modeling Proposed Airflow?NC-2009 EAc1: Optimize Energy Performanceposted by Barbara McCrary on Oct 18, 2010, 4:23 pm
I started a previous thread on DX systems. Let me step back and see if anyone can help me with my larger question - Do we have to model the design airflow rate of our proposed system? A comment... Last reply: Michael Tillou, Oct 19, 2010, 11:59 am |
|
Documentation ToolkitEBOM-2009 MRp1: Sustainable Purchasing Policyposted by Robin Obaugh on Oct 18, 2010, 7:01 pm
Silly question I know, but when utilizing the "template" for the Sustainable Purchasing Policy, should we delete the header and footers related to LEED User? Last reply: Robin Obaugh, Oct 19, 2010, 11:56 am |
|
Modeling DX systems with set cfm/ton constraintsNC-2009 EAc1: Optimize Energy Performanceposted by Barbara McCrary on Oct 18, 2010, 1:48 pm
I was wondering if anyone had experience modeling DX systems in their proposed systems. I received a USGBC comment that the actual airflow had to be modeled, auto-sizing was not allowed. My... Last reply: Michael Tillou, Oct 19, 2010, 11:49 am |
|
Ineligible intersectionsPilot-Credits PC9: Street Networkposted by Michael Miller on Oct 19, 2010, 11:36 am
I would suggest that intersections that only serve on-/off-ramps for controlled-access highways also be excluded from being counted for this credit. |
|
EQc6.1 for multi-occupant spacesCI-2009 IEQc6.1: Controllability of systems - lightingposted by Michele Helou on Oct 4, 2010, 12:55 pm
Does anyone know if multi-occupant spaces such as exhibit spaces or lecture rooms without... Last reply: Danuta Drozdowicz, Oct 18, 2010, 9:30 pm |
|
LEED OnlineEBOM-2009 WEp1: Minimum Indoor Plumbing Fixture and Fitting Efficiencyposted by Paul C on Sep 20, 2010, 10:29 am
I want to make sure I am understanding this correctly in filling out LEED Online, I am a little confused when filling out LEED Online: -I have an multi-tenant office building so everyone... Last reply: Dan Ackerstein, Oct 18, 2010, 6:42 pm |
|
Performance Period MeteringEBOM-2009 WEc3: Water Efficient Landscapingposted by Matthew Macko on Oct 5, 2010, 1:56 pm
I have a project that has recently had an irrigation metered installed, but unfortunately it happened after July. The project is running from October to January and cannot be extended through... Last reply: Dan Ackerstein, Oct 18, 2010, 6:32 pm |
|
Hot and humid areaCS-2009 EAc1: Optimize Energy Performanceposted by javier bolanos zeledon on Oct 15, 2010, 12:03 am
I have a CS V2.0 office building project in a hot an humid area, climate zone 3C as per Ashrae. Last reply: javier bolanos zeledon, Oct 18, 2010, 11:15 am |
|
questions about LEED reviewer comments at EAp2NC-2009 EAp2: Minimum Energy Performanceposted by Florian Schmidtchen on Sep 27, 2010, 12:21 am
hello folks, I just received the comments from the reviewer and have some questions about them. The reviewer questioned a lot about the fan power simulation. Q1. AppendixG assumes... Last reply: Christopher Schaffner, Oct 16, 2010, 1:58 pm |