LEED CI inside a LEED C&S certified buildingCI-2009 SSc3.2: Alternative transportation - bicycle storage and changing roomsposted by Cinthia Kawano on Aug 6, 2013, 4:10 pm
We are dealing with a Commercial Interior Project, which is located inside a LEED C&S certified building. Regarding the credit SSc3.2, the attendance of the LEED C&S building (SSc4... Last reply: David Posada, Aug 14, 2013, 3:40 pm |
|
Existing bike storage and showersCI-2009 SSc3.2: Alternative transportation - bicycle storage and changing roomsposted by Peter Doo on Nov 17, 2009, 5:16 pm
The project is a radiology suite within an existing urban hospital so, not exactly a tenant. The hospital has existing bicycle storage. Once we determine the required # of bicycles required for... Last reply: emily reese moody, Jun 5, 2013, 10:41 am |
|
Showering and Changing Facilities in Men´s BathroomCI-2009 SSc3.2: Alternative transportation - bicycle storage and changing roomsposted by Silvia Ruiz on Apr 24, 2013, 8:48 pm
Hi, I am working on a small project that only requires one shower, but due to space constraints, the shower and changing room have been located inside the men's bathroom facilities. Do you... Last reply: Silvia Ruiz, Apr 25, 2013, 12:15 am |
|
Changing roomsCI-2009 SSc3.2: Alternative transportation - bicycle storage and changing roomsposted by MARIA GARCIA on Apr 8, 2013, 11:41 am
Hi all, Last reply: David Posada, Apr 11, 2013, 1:27 pm |
|
Off site bicycle storage and shower facilityCI-2009 SSc3.2: Alternative transportation - bicycle storage and changing roomsposted by James Wilson on Jul 28, 2010, 11:17 am
We are doing our own office as a CI upfit in a building. We will not have on-site bicycle storage and showers, but we have a YMCA 200 yards away, which should quality. Last reply: Misc User, Feb 22, 2013, 3:02 pm |
|
Communal cycle spacesCI-2009 SSc3.2: Alternative transportation - bicycle storage and changing roomsposted by Eszter Gulacsy on Dec 20, 2012, 12:10 pm
We are currently working on a LEED-CI project, in which there is no cycle storage planned / available within the project area, however, there is ample cycle racks near to the site. When I mean... Last reply: David Posada, Jan 2, 2013, 8:10 pm |
|
New LEED CI SScr3CI-2009 SSc3.2: Alternative transportation - bicycle storage and changing roomsposted by Kevin Wilcox on Jun 11, 2012, 12:22 pm
I recently completed a LEED CI project and submitting for review and just started a new LEED CI project under LEED CI v2009 and found a significant change to the SS credit 3 category. Can anyone... Last reply: David Posada, Jun 19, 2012, 7:08 pm |
|
SS c.3.2 Secure Bicycle Storage instead of bicycle racksCI-2009 SSc3.2: Alternative transportation - bicycle storage and changing roomsposted by Kasia Trojanowska on May 14, 2012, 1:23 pm
We identified secure bicycle storage with pass code locker for exclusive use of project's occupants within a garage... Last reply: David Posada, Jun 13, 2012, 3:56 pm |
|
Shower AccessCI-2009 SSc3.2: Alternative transportation - bicycle storage and changing roomsposted by Matthew Macko on Feb 16, 2012, 8:23 pm
I have a dental office project located in a residential condo tower. There is a health/fitness club in this tower that has showers located in them. All residents of the tower, including the... Last reply: Robyn Vettraino, Jun 7, 2012, 11:54 am |
|
Approaching SSc4.2 w/ Alt Compliance Using LEED Retail GuidanceCI-2009 SSc3.2: Alternative transportation - bicycle storage and changing roomsposted by Taylor Ralph on Jan 18, 2012, 3:32 pm
Has anyone had any success approaching this credit using the Retail requirements--where it is only required to provide lockable changing rooms? There may be a... Last reply: Taylor Ralph, Jun 7, 2012, 11:02 am |