Exemplary Performance- forms questionNC-2009 MRc2: Construction Waste Managementposted by André Knutsson on Sep 19, 2011, 8:09 am
We have finished the project whith a 97.2 % recycling, and are pursuing the one Innovation in Design credit. When we register the IDc1.1 we do not get to choose the MRc2 in the dropdown window... Last reply: André Knutsson, Sep 28, 2011, 2:40 am |
|
landfill has a recycle/reuses program in placeNC-2009 MRc2: Construction Waste Managementposted by ming zeng on Sep 26, 2011, 5:21 pm
We have a project that the local landfill has a recycle/... Last reply: Tristan Roberts, Sep 27, 2011, 10:47 am |
|
Pavement and TreesNC-2009 MRc2: Construction Waste Managementposted by Michelle Teague on Sep 8, 2011, 9:46 pm
The definition of construction and demolition debris on page 362 of the technical guide says "pre-existing structures". I understand the exclusion of land clearing debris, such as soil,... Last reply: Tristan Roberts, Sep 26, 2011, 10:32 pm |
|
Construction Waste Management || Clean FillNC-2009 MRc2: Construction Waste Managementposted by Andrew Gil on Aug 29, 2011, 1:19 pm
Apologies if this topic has already been addressed (and, on that note, I have a suggestion: As the number of postings grows & grows, it might be very helpful to be able to search within a... Last reply: Susan Walter, Sep 14, 2011, 1:49 pm |
|
Modern methods of constructionNC-2009 MRc2: Construction Waste Managementposted by Bradley Guy on Aug 20, 2011, 5:54 pm
In its current form the MRc2 is for diverting waste that has been created, it does not credit 'preventing' waste, however please take a look at the LEED 2012 2nd public comment version of this... Last reply: Susan Walter, Aug 29, 2011, 1:46 pm |
|
third-party verification of landfill diversion docs (re-post)NC-2009 MRc2: Construction Waste Managementposted by Jeff Jones on Jul 12, 2011, 2:30 pm
I am considering submitting a Pilot LEED Credit for verifying (or certifying) the actual recycling of building waste materials, whether it is from construction or an... Last reply: Bradley Guy, Jul 25, 2011, 7:11 pm |
|
Split Site RecyclingNC-2009 MRc2: Construction Waste Managementposted by Jon Texter on Jun 13, 2011, 12:07 pm
We are working on a 10 building apartment complex, which consists of 9 Residential Buildings and a Community Building. The Community building is attempting LEED NC Silver, but the Residential... Last reply: RETIRED, Jun 28, 2011, 11:36 am |
|
Tracking / documenting items being reused from demo'd bldgNC-2009 MRc2: Construction Waste Managementposted by Renee Shirey on May 20, 2011, 11:03 am
On our site we have several items that will be salvaged from our demo'd building/site (furniture, playground equipment) that will be used with the new building/site. How do we track this so we... Last reply: Valerie Walsh, May 26, 2011, 5:56 pm |
|
Construction Waste Theft!NC-2009 MRc2: Construction Waste Managementposted by Jeffrey Westall on May 26, 2011, 11:35 am
We are having a serious issue with all of our metal scrap being stollen from the jobsite dumpster. This has impacted our percentage for recycling dramatically. We are currently at only 28%.... Last reply: Renee Shirey, May 26, 2011, 5:31 pm |
|
TreesNC-2009 MRc2: Construction Waste Managementposted by Norma Lehman on May 9, 2011, 9:03 am
We are removing a lot of trees on our construction site, if we turn it into mulch does this qualify toward our... Last reply: Valerie Walsh, May 26, 2011, 5:29 pm |