posted by Yu Wang on Feb 4, 2013, 10:39 am

I'm working on an option D M&V plan according to LEED. The building is heated and cooled with gas heat pump, therefore the electricity consumption just includes fan/pump power, process load...

Last reply: Marcus Sheffer, Feb 4, 2013, 2:08 pm

illumination metering with a photovoltaic system?

NC-2009 EAc5: Measurement and Verification
posted by Tatiana Machado on Jan 22, 2013, 10:38 am

A project illumination system is controlled by a photovoltaic system. This system has a rechargeable battery as its primary energysource and as an auxiliary source it utilizes grid power.
...

Last reply: Marcus Sheffer, Jan 22, 2013, 5:39 pm

Submetering of each ECM

NC-2009 EAc5: Measurement and Verification
posted by Jatuwat Varodompun on Dec 12, 2012, 11:02 pm

Can the submeters for optionD are only provided to cover all ECMs. For instance, if we aim to measure the pump energy, the submetering for the pumps will be provided. On the contrary, if we don't...

Last reply: Jatuwat Varodompun, Dec 13, 2012, 5:43 pm

Submetering

NC-2009 EAc5: Measurement and Verification
posted by Jatuwat Varodompun on Dec 12, 2012, 4:05 am

For Option D, do we need submetering? and can it be analyzed using only whole building energy? if we required submetering, what level we have to monitored eg HVAC, lighting, process? do we have...

Last reply: Marcus Sheffer, Dec 13, 2012, 9:37 am

EAc5 Option 3

NC-2009 EAc5: Measurement and Verification
posted by Crina Bosch on Dec 3, 2012, 11:49 am

We have a large project that is on a...

Last reply: Marcus Sheffer, Dec 3, 2012, 12:27 pm

EAc5 Exemplary Performance

NC-2009 EAc5: Measurement and Verification
posted by Jodie Clarke on Nov 8, 2012, 5:20 pm

The guidance for exemplary performance specifies the NC, CS and Schools rating systems. I would like to get credit for following Option 2 and 3 for Healthcare. Does anyone know if...

Last reply: Marcus Sheffer, Nov 8, 2012, 5:46 pm

M&V baseline for retrofit?

NC-2009 EAc5: Measurement and Verification
posted by Eric Longfellow on Jun 12, 2012, 7:49 pm

Hi, we are working on a extensive renovation of a 80,000 SF university classroom/office building using LEED NC 2009. Most of the mechanical cooling will be removed and it will be restored to...

Last reply: Eric Longfellow, Sep 24, 2012, 8:13 pm

LEED MV Credits compliance with Option D

NC-2009 EAc5: Measurement and Verification
posted by Ameet AA on May 15, 2012, 9:38 am

To achieve this credit, during the CONSTRUCTION Stage we just have to submit the...

Last reply: Tristan Roberts, May 15, 2012, 12:49 pm

"required" metered systems

NC-2009 EAc5: Measurement and Verification
posted by Florian Schmidtchen on Mar 29, 2012, 5:17 am

On this webpage in EAc5, I read that there are "Commonly metered systems", including lighting , motors, HVAC loads etc. In my case a part of items in this list seem not helpful on the model...

Last reply: Marcus Sheffer, Mar 29, 2012, 10:28 am

Sample of Measurement and Verification report for Option B?

NC-2009 EAc5: Measurement and Verification
posted by Eric JS on Feb 22, 2011, 11:59 am

Dear all,

Do you have any sample of Measurement and Verifiation report for Option B?

Thank you and cheers!

Last reply: Marcus Sheffer, Mar 20, 2012, 3:04 pm