posted by Abdulla Anwar on Feb 23, 2017, 9:10 am

Our MEP sub-contractor need to clarify if we can use an smoke capsule for duct leakage test? prior to air leakage test since the project specs is giving a small allowable 1% from...

Last reply: Scott Bowman, Feb 27, 2017, 4:11 pm

Concerning Signatories

NC-2009 EAc3: Enhanced Commissioning
posted by Omar Elrawy on Jan 23, 2017, 8:12 am

I need to know if the two signatories on the EA CREDIT 3: ENHANCED COMMISSIONING - LEEDOnline form are to be signed by the...

Last reply: Scott Bowman, Jan 30, 2017, 5:55 pm

Enhanced Cx- EAc3;

NC-2009 EAc3: Enhanced Commissioning
posted by Miles Britz on Oct 6, 2016, 1:41 pm

Systems Manual; on our Const. Phase submittal the reviewer stated we need to include a Systems Manual. It appears this refers to the Training of staff on the bldg.'s. commissioned ME & P...

Last reply: Scott Bowman, Oct 21, 2016, 3:57 pm

CxA role

NC-2009 EAc3: Enhanced Commissioning
posted by Abdulla Anwar on Aug 8, 2016, 6:17 am

Can you advise the...

Last reply: Scott Bowman, Aug 9, 2016, 11:27 am

Enhance commissioning

NC-2009 EAc3: Enhanced Commissioning
posted by Mamdooh Amin on Aug 8, 2016, 3:57 am

Do we have to include the contract document between the owner and the...

Last reply: Scott Bowman, Aug 9, 2016, 11:07 am

Signed Contract with the CxA

NC-2009 EAc3: Enhanced Commissioning
posted by Mohamed M. Abd Elhameed on Jul 1, 2015, 4:22 am

We are pursuing LEED Certification for a 476921.20 sq ft Mixed Use Office Building in Egypt.

Building Owner is a multinational design firm who do both tasks, the project design and the...

Last reply: Scott Bowman, Jun 30, 2016, 4:51 pm

Major Change to Who Can Be a CxA!

NC-2009 EAc3: Enhanced Commissioning
posted by Scott Bowman on Jul 28, 2014, 12:16 am

I was trying to do some catching up, and the July Addenda has a very significant change to who can be the...

Last reply: Scott Bowman, Jun 10, 2016, 11:20 am

EAc3- Enhanced Commissioning, LEED v2009

NC-2009 EAc3: Enhanced Commissioning
posted by Jared Reed on Apr 22, 2016, 1:50 pm

Our project is pursuing EAc3 - Enhanced Commissioning. The reference manual states that the...

Last reply: Scott Bowman, May 2, 2016, 11:37 am

How to apply the enhanced commissioning task to existing?

NC-2009 EAc3: Enhanced Commissioning
posted by Dave Hubka on Mar 29, 2016, 9:10 am

Hi Scott,

We are involved with a major addition to an existing building. We will be certifying the entire building. How do you recommend we apply the enhanced...

Last reply: Dave Hubka, Apr 2, 2016, 10:22 am

District Energy System owned by Government vs. Owner

NC-2009 EAc3: Enhanced Commissioning
posted by Erin Holdenried on Jun 14, 2011, 3:41 pm

My question is in regard to both EAc3: Enhanced Commissioning and EAc5: Measurement and Verification credits in relation to a District Energy System. We are working on a project based in China...