29.47% reduction question...NC-2009 WEc3: Water Use Reductionposted by Rick Alfandre on Nov 20, 2013, 4:25 pm
We had an initial mis-characterization of our flow fixtures (we thought they were private, not public), and now with everything properly calculated we are at 29.47% reduction from base case.... Last reply: Tristan Roberts, Dec 20, 2013, 4:03 pm |
|
ReviewNC-2009 WEc3: Water Use Reductionposted by Alicia Villanueva on Jun 4, 2013, 12:44 pm
My project has achieved a 82% savings in flow & flush fixtures through recycling 100% of the waste water and reusing it for WC and urinal flushing. We documented this with a... Last reply: Tristan Roberts, Nov 3, 2013, 2:00 pm |
|
Existing FixturesNC-2009 WEc3: Water Use Reductionposted by ERIC TAYLOR on Oct 21, 2013, 5:58 pm
Do I have to account for the water use of existing fixtures to remain on a major renovation (football stadium) under LEED NC, if they are within the LEED boundary, but the spaces/structures they... Last reply: ERIC TAYLOR, Oct 24, 2013, 4:30 pm |
|
laboratory sinksNC-2009 WEc3: Water Use Reductionposted by Bryan Waters on Oct 9, 2012, 5:35 pm
Our project is a 50% office- 50% lab building. Are laboratory sinks to be accounted for in this credit calculation? Thanks. Last reply: Carlie Bullock-Jones, Oct 14, 2013, 11:41 am |
|
Dual toilet flush rate averageNC-2009 WEc3: Water Use Reductionposted by Mike D on Aug 19, 2013, 11:43 am
If we were to calculate the average flush rate of a dual flush toilet (with urinals present in the space) we use the example average flow rate equation provided by USGBC in their Appendix A water... Last reply: Carlie Bullock-Jones, Aug 19, 2013, 11:50 am |
|
water efficiency reviewNC-2009 WEc3: Water Use Reductionposted by Shristi Bajracharya on Jun 9, 2013, 2:38 am
When we sent the WE credit for review for our project, we sent a water use calculation stating that the potable water usage in the project has been reduced by 43% from a calculated baseline... Last reply: Susan Walter, Jun 10, 2013, 1:35 pm |
|
WEc3 & WEc2 linked?NC-2009 WEc3: Water Use Reductionposted by Faith Wilbert on Apr 12, 2013, 2:50 pm
I have completed the form for WEp1 & WEc2. When I go to finish WEc3 it doesn't show the savings from the... Last reply: Erin Holdenried, Apr 15, 2013, 2:41 pm |
|
Apportioning Rainwater between WEc1, WEc2 and WEc3NC-2009 WEc3: Water Use Reductionposted by Lewis Hewton on Mar 22, 2013, 12:19 am
Hi all, For some background on our project: - we have on-site rainwater capture as well as connection to a municipal non-potable water supply |
|
Dual Flow faucetNC-2009 WEc3: Water Use Reductionposted by mariela garate on Mar 20, 2013, 5:36 pm
The water use of dual flow faucets that has two positions, would be a weighted average of both? As a dual flush toilet water use is... |
|
Rainwater collection (kGal) calculations for LEEDNC-2009 WEc3: Water Use Reductionposted by Ameet AA on Feb 25, 2013, 12:35 pm
Is there a calculator tool or methodology that we should use when submitting our annual rainwater collection (kGal) calculations for LEED? Our calculations are currently based on BS 8525... Last reply: Tristan Roberts, Feb 25, 2013, 2:43 pm |