Heat Island Effect for Existing Roof to Remain

NC-v4 SSc5:Heat island reduction
posted by  Allen Cornett  on 

How do you account for an existing roof greater than 3 years old that will remain?  Can the aged values in the manufacturer's literature be used in the calculations?

1
Mon Nov 19, 2018, 10:20 pm

VA project Guiding Principles checklist

LEED Rating System Selection
posted by  Kasandra Martin  on 

I am working on a VA federal job of Non Recurring Maintenance.  Is there a forum for this or anyone that has worked on one??

0
2