IN vs. Exemp Performance Documentation Review

NC-v4 INc1: Innovation
posted by Tracy Jordre on Dec 30, 2018, 10:23 pm

We would like to wait until the Prelim Construction Submittal to submit our Innovation credits for review.  In our preliminary design submittal, we did not mark the Innovation credit as “ready to...

Last reply: emily reese moody, Jul 11, 2019, 11:29 pm

Purchasing Lamps Innovation Credit

NC-v4 INc1: Innovation
posted by Jason Garvens on Jan 19, 2018, 12:25 pm

For the Purchasing Lamps Innovation credit the requirements section states: "Must meet the exemplary performance criteria of the base credit (an average 35 picograms per lumen hour or less)."...

Last reply: emily reese moody, Jul 11, 2019, 11:25 pm

Green Cleaning no longer an option?

NC-v4 INc1: Innovation
posted by emily reese moody on Jan 25, 2018, 6:27 pm

Hi all, 

I was just looking for the criteria for Green Cleaning for my v4 NC project, but do not see it listed on USGBC in neither the Innovation Catalog, nor the Pilot Credits. I double-...

Last reply: Trista Little, May 16, 2019, 8:19 pm

Aerobic Digester for a LEED credit?

NC-v4 INc1: Innovation
posted by Harry Flamm on Jan 31, 2018, 3:32 pm

On a university residential/dining hall project, we will be utilizing an "Eco-Digester", (an aerobic digester from BioHiTech), http://...

Last reply: Han Qiang Ler, May 14, 2019, 1:37 am

ISO 14001 Certified EMS- Innovation Credit?

NC-v4 INc1: Innovation
posted by Miguel Rivera on May 7, 2019, 3:30 pm

Reposting this question from LEED 2009. Has anyone received guidance on whether this is an acceptable Innovation credit (ISO 14001 Certified EMS) for LEEDv4 projects? 

Thanks, 

Passive Survivability and Back-up Power During Disruptions

NC-v4 INc1: Innovation
posted by Ridhwan Omar on Mar 29, 2019, 10:42 am

Hello LEEDUsers!

We have a resort hotel project in one of the islands in Micronesia.

Due to reliability problems with the electricity system on the island and the lack of reserve...

Quality views in nonregularly occupied spaces

NC-v4 INc1: Innovation
posted by keerthana gopi on Feb 27, 2019, 8:41 am

One of our projects is a 30-storey building. The credit requires 15% of non regularly occupied floor area to have access to views. Is there any expected pattern for floor-wise distribution or can...

Integrative Process for Health Promotion

NC-v4 INc1: Innovation
posted by Peter Doo on Feb 19, 2019, 2:59 pm

Looking for anyone who has done or attempted to do this credit. Seems like an incredible amount of work for 1 point. we are estimating half the amount of effort as the entire LEED project...

Walkable Project Site

NC-v4 INc1: Innovation
posted by Graciela Quiles Gonzalez on Feb 13, 2019, 2:00 pm

Are facades of existing buildings (not historic) exempt of Requirement number 8 of the Walkable Project Site? 

Requirement 8: "No more than 30% of the primary facade at ground level is...

IPpc100 Passive Survivability and Functionality during Emergencies

NC-v4 INc1: Innovation
posted by Noriko Yasuhara on Jan 29, 2019, 2:44 am

Hi,

We are submitting this pilot credit via Option 2: Provide Backup Power for critical loads. The project building is office usage, but there is no instruction for office building...