Option 1, Path 3. Streamlined DES Modeling
NC-v4 EAp2:Minimum energy performanceposted by Nasim Mirian on
Hi,
I am trying to submit for LEED v4 for a campus building which is served by the campus central plant.we are taking Option 1, Path 3. Streamlined DES Modeling.
Inherently Nonemitting
NC-v4.1 EQc2:Low-Emitting Materialsposted by Allen Cornett on
Recently I saw the following preliminary-review comments on a colleague’s project:
ASHRAE 90.1-2007 Lighting Power Density
NC-2009 EAp2:Minimum Energy Performanceposted by Arub Vijay on
Dear All, I have a doubt regaridng the LPD requirements for LEED projects. I am doing a Hotel project and would like to know if its mandatory to comply with Table 9.5.1 and Table 9.6.1 for LPD.
VOC limit of Aerosol Adhesives
NC-v4 EQc2:Low emitting materialsposted by L W on
Hi All,In LEED v4 and 4.1, is there a limit on the VOC content of aerosol adhesives, and if so what is it?
Building Performance Factors
CS-v4.1 EAc2:Optimize Energy Performanceposted by Michael Brown on
Per Table 2.4 Building Performance Factors (BPF) for Complaicne with Standard 90.1-2016, if you have a mixed use building I assume that you would use the weighted averge (based on GSF) of each majo
Exceptional calculation method application.
NC-2009 EAp2:Minimum Energy Performanceposted by FABIO VIERO on
Under ASHRAE 90.1 – G2.5, can we avoid to use a workaround to detail a HVAC system feature which could involve an energy saving, therefore avoid to do an exceptional calculation method, if we prefe
Swimming Pools Baseline Definition
NC-v4 EAp2:Minimum energy performanceposted by Ricardo Sá on
Dear All,
USGBC's commentary "Product Replacement via EPDs optimization"
NC-v4.1 MRc1:Building Life-Cycle Impact Reductionposted by jaclyn lee on
We got a comment back from USGBC that said this:
Rainwater tank for irrigation
NC-v4 WEp1:Outdoor water use reductionposted by Julio Fernandez Amodia on
Historical building and Existing building part of connected structure
NC-v4 MRc1:Building life-cycle impact reductionposted by Edgar Arevalo on
I have courthouse project that involves two existing buildings being connected with a newly constructed third building. Since one of the existing buildings connected to the third one is class