Waste-to-EnergyNC-v4 MRc5: Construction and demolition waste managementposted by Lise Dannesboe on Jan 9, 2018, 4:06 amand recycling strategies were exhausted before sending waste material to energy facilities." The credit form has a text box for your explanation. Lastly, I hope you saw this forum- https://leeduser.buildinggreen.com/forum/incineration-option-diversion-m... Log in or register to post comments ... Last reply: RETIRED, Jan 9, 2018, 1:27 pm |
|
Material ReuseNC-v4 MRc5: Construction and demolition waste managementposted by SAMY Chamy on Dec 27, 2017, 7:29 amto a new one." Please post your second question about how to enter this material into the BPDO calculator in the forum related to that credit (BPDO- Sourcing of Raw Materials)- ... Last reply: RETIRED, Dec 28, 2017, 9:40 am |
|
calculating the diverted & total wasteNC-v4 MRc5: Construction and demolition waste managementposted by sara m on Nov 11, 2017, 12:08 pm
hello, i have a question in how to calculate the diverted and total waste in option 1 path 2 ( 75% ) if we have different units?? and i read that units can be only for weight or volume,... Last reply: RETIRED, Nov 12, 2017, 9:54 am |
|
Waste unit conversionNC-v4 MRc5: Construction and demolition waste managementposted by Charline SEYTIER on Sep 26, 2016, 8:43 am
We’re currently working on a project that is following option one for this credit and calculating the... Last reply: RETIRED, Sep 26, 2016, 8:19 pm |
|
land clearing debris, soil, etcNC-v4 MRc5: Construction and demolition waste managementposted by Jen Roberts on Nov 7, 2015, 3:21 pm
On page 591 of the ref guide, it states... Last reply: RETIRED, Apr 7, 2016, 10:47 am |
|
StreamsNC-v4 MRc5: Construction and demolition waste managementposted by Charalampos Giannikopoulos on Jul 14, 2015, 6:08 am
In PR prerequisite it is required that 5 materials have been identified for diversion. If for the credit only 4 steams have been used would this discrepancy cause a problem towards compliance... |
|
Option 2- "Waste" reductionNC-v4 MRc5: Construction and demolition waste managementposted by Whitney Smith on May 26, 2016, 2:25 pm
In option 2 of this credit, does the 2.5 pounds of "waste" mean 2.5 pounds of non diverted waste? Or is it all refuse- recycled, salvaged, reused, incinerated, and landfilled cannot... Last reply: RETIRED, May 31, 2016, 11:03 am |
|
Does this count for LEED Credits?NC-v4 MRc5: Construction and demolition waste managementposted by James Goldfield on Jun 7, 2016, 12:28 pm
I am on a site where we have the option to chip the fallen tree's and stumps and sell that material to a power plant. Will tracking the amount of debris that is chipped count towards LEED Credit... Last reply: RETIRED, Jun 8, 2016, 11:11 am |
|
Exemplary Performance Over 95% DivertedNC-v4 MRc5: Construction and demolition waste managementposted by Cynthia Kaplan on Sep 20, 2016, 4:54 pm
Has this bonus point gone away? There is no longer a point awarded for achieving a diverted rate over 95%? Last reply: RETIRED, Sep 25, 2016, 11:12 am |
|
Manufacturer Take Back ProgramsNC-v4 MRc5: Construction and demolition waste managementposted by Leanne Conrad on Oct 31, 2016, 10:17 am
I am looking for information on what type of backup documentation is required when we choose to use a manufacturer take back program as part of our recycling program. What information will the... Last reply: RETIRED, Oct 31, 2016, 12:09 pm |