Healthcare-v2009 MPR3: Must use a reasonable site boundary
posted by Kath Williams on Mar 23, 2016, 1:32 pm

Our project preliminary review points toward gerrymandering the LEED project boundary. It is a golf course clubhouse with geothermal pond on an existing putting green and paths. We included a...

Existing road

Healthcare-v2009 MPR3: Must use a reasonable site boundary
posted by Heather Holdridge on Mar 15, 2016, 11:50 am

The development (landscape and new chiller yard) associated with our LEED project reaches across a road that is owned by the city and not the client. Should the road be a part of our LEED...

Shared underground parking with non LEED certified buildings

Healthcare-v2009 MPR3: Must use a reasonable site boundary
posted by Jorge Lopez de Obeso on Mar 2, 2016, 10:49 am

Our project, a 200,000 sqft CS office tower (much more to the 20% of the total area) shares 3 levels of underground parking lot with two other buildings (Movie theater, shops, restaurants). All...

Two Identical Buildings

Healthcare-v2009 MPR3: Must use a reasonable site boundary
posted by Paula Hernandez on Feb 16, 2016, 6:03 am

Hi, we want to achieve the Precertification for a CS project.
There are two office buildings, almost identical, on the same parcel. They share four underground parking levels. We want to...

LEED Boundary and Non-contiguous reconfigured areas

Healthcare-v2009 MPR3: Must use a reasonable site boundary
posted by Aaron Ketner on Feb 15, 2016, 5:14 pm

Our project is currently registered under NC 2009. This 66,500sf project consists of a new classroom addition to an existing 53,000sf building, which achieved LEED silver under NC 2.2. The...

Pump Room, STP Room & Guard Room Within LEED Boundary

Healthcare-v2009 MPR3: Must use a reasonable site boundary
posted by Aswin M on Dec 31, 2015, 4:54 am

We have a factory project to be registered under LEED New Construction. The project has a Main building and additionally Pump room, STP room and a guard room which serves the need of the Main...

Last reply: Aswin M, Feb 5, 2016, 4:41 am

Campus road

Healthcare-v2009 MPR3: Must use a reasonable site boundary
posted by Susan Di Giulio on Apr 24, 2015, 8:27 pm

We have a project on a university campus. The university maintains the roads on the campus, although there is public access 24/7.
Our building site has a minor campus road/driveway to...

Last reply: Jon Clifford, Nov 28, 2015, 8:57 am

LEED Boundary adjacent to the Ocean

Healthcare-v2009 MPR3: Must use a reasonable site boundary
posted by Thomas Ehrnschwender on Nov 10, 2015, 2:00 pm

Project is adjacent to the Atlantic Ocean. The sand dune is protected with many native plant species and a nesting habitat for 5 different endangered turtle species. Can the water line define...

Last reply: Tristan Roberts, Nov 26, 2015, 10:44 pm

Non-certifiable Parking Garage within LEED Boundary

Healthcare-v2009 MPR3: Must use a reasonable site boundary
posted by natalie tan on May 21, 2014, 10:30 am

We are seeking LEED certification for a new office building. A new separate parking garage building (under the same construction contract) falls within the LEED Boundary. I understand that the...

Last reply: Michelle Ray, Oct 8, 2015, 5:34 pm

Phasing Multiple LEED Projects

Healthcare-v2009 MPR3: Must use a reasonable site boundary
posted by Sara Zoumbaris on Oct 2, 2015, 12:30 pm

We are working on a development where the project site is composed of two adjacent parcels of land. There are four-buildings total on this site (3 new and 1 a major renovation) that are pursuing...