Topic | Recent |
---|---|
Ashrae 90.1, section 6.4 minimun equipment efficienciesCS-2009 EAp2: Minimum Energy Performanceposted by Agustin Bertolotti on May 19, 2011, 3:28 pm
Hello everyone Last reply: Christopher Schaffner, Nov 15, 2011, 9:32 am |
|
Mandatory provision in LEED CSCS-2009 EAp2: Minimum Energy Performanceposted by Roger Moquin on Nov 9, 2011, 11:40 am
We actually construct a high rise office building with commercial area at the first level. One of our projected commercial tenant want to modify his frontage, that we previously made, by adding... Last reply: Roger Moquin, Nov 9, 2011, 2:37 pm |
|
Insulation requirementsCS-2009 EAp2: Minimum Energy Performanceposted by Gabriela Hernández Castillo on Nov 1, 2011, 6:34 pm
Our LEED building consits on an 39 stories speculative office building that is on top of a 3 stories retail building. The retail will not apply for LEED certification. The retail's roof... Last reply: Gabriela Hernández Castillo, Nov 8, 2011, 3:37 pm |
|
Building RenovationCS-2009 EAp2: Minimum Energy Performanceposted by Morteza Kasmaei on Nov 2, 2011, 3:15 pm
Advanced Energy Modeling for LEED states "Existing buildings with less than 50% renovation should not be rotated,...". How can one calculates renovation percentage of an existing building? Last reply: Marcus Sheffer, Nov 4, 2011, 10:17 am |
|
DoubtCS-2009 EAp2: Minimum Energy Performanceposted by Redy Truccolo on Sep 14, 2011, 12:16 pm
Hi, I'm doing a LEED CS 2009 PRE-certification. In the "Upload L-4" section, which states: Last reply: Christopher Schaffner, Oct 26, 2011, 3:24 pm |
|
Process Costs Tables for C&SCS-2009 EAp2: Minimum Energy Performanceposted by Maya Karkour on Oct 19, 2011, 9:12 am
Dear all, I am modeling a C&S project (large shopping mall). For the process loads, I am using: Last reply: Marcus Sheffer, Oct 19, 2011, 10:03 am |
|
Upload EAp2-11CS-2009 EAp2: Minimum Energy Performanceposted by Morteza Kasmaei on Oct 15, 2011, 1:16 pm
I'm using eQUEST for my project. I should upload certain documents for LEED review including "Input Summary". Do I have to create a summary report or there is a summary report within the eQEST... Last reply: Marcus Sheffer, Oct 15, 2011, 2:42 pm |
|
diesel generator on-siteCS-2009 EAp2: Minimum Energy Performanceposted by Johannes Gellrich on Oct 14, 2011, 9:25 am
Hi everyone, Last reply: Marcus Sheffer, Oct 14, 2011, 5:55 pm |
|
ASHRAE 90.1 APPENDIX G Existing Building Model including shadingCS-2009 EAp2: Minimum Energy Performanceposted by Fabiano Castro on Sep 26, 2011, 4:56 pm
We are modelling a Major Renovation Project under the ASHRAE 90.1-2007 - APPENDIX G. The building existing conditions prior to this project renovation includes solar shading devices on all... Last reply: Marcus Sheffer, Oct 1, 2011, 12:32 pm |
|
Record Time for ASHRAE appx G Simulation?CS-2009 EAp2: Minimum Energy Performanceposted by Jean Marais on Aug 11, 2011, 12:33 pm
What's your record time? What software did you use? Last reply: Marcus Sheffer, Sep 30, 2011, 8:04 pm |