Post a question or comment
Filter by location
Forum
Topic
Replies
Recent

Recycled Soil and Aggregate

NC-2009 MRc4:Recycled Content
posted by  Lyle Axelarris  on 

I've just learned of a company that remediates contaminated soil and aggregate and then sells the material (for cheaper than virgin material).

7
Default Avatar
Architect
RSP Architects Ltd.
LEEDuser Basic Member
14 thumbs up
Wed May 22, 2013, 1:23 pm

Tenant spaces

CS-2009 EAp2:Minimum Energy Performance
posted by  PAWAN DAHIWAL  on 

I am working on CS project..i have small doubt If tenant spaces (HVAC, LIGHTING etc) comes under owner/developer scope of work, those spaces should be model as per ASHRAE (in baseline).

3
Default Avatar
Min engineering inc
LEEDuser Basic Member
2 thumbs up
Tue May 21, 2013, 3:45 pm

FSC certification for drywall subs

NC-2009 MRc7:Certified Wood
posted by  Doreen Kruschina  on 

In an industrial project the GC uses a sub for all his interior wall partitions in the office building. This sub wants to use certified doors frames and slabs.

2
Principal
Jason Grant Consulting
LEEDuser Expert
115 thumbs up
Tue May 21, 2013, 11:52 am

Major renovation zero-lot line project has oil spillage...

NC-2009 SSc3:Brownfield Redevelopment
posted by  Maria Porter  on 

...in the intermediate floors An old building will undergo a major renovation.

2
Principal
Studio4, LLC
LEEDuser Expert
120 thumbs up
Tue May 21, 2013, 6:45 am

Electric car charger

NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  Noriko Nagazumi  on 

Hi, Our project is planning to go option2, providing electric charger for vehicles. Are there any requirments for elecric charger, such as mesuring electricity or billing?

2
Tue May 21, 2013, 12:53 am

Material reuse in concrete

NC-2009 MRc4:Recycled Content
posted by  Mahbuba Khan AIA, LEED AP BD+C  on 

Three question regarding recycled content in concrete: *If the concrete contains brick chips from reused bricks will it count towards recycled content.

2
Default Avatar
Architect
RSP Architects Ltd.
LEEDuser Basic Member
14 thumbs up
Mon May 20, 2013, 8:25 pm

Commingled Review Comment

NC-2009 MRc2:Construction Waste Management
posted by  Michelle Rosenberger  on 

We recently received this clarification from a reviewer who expressed confusion about the monthly diversion rate backup that we supplied from our receiver for commingled diversion. "Monthly commin

5
Mon May 20, 2013, 2:19 pm

Percantage Make-Up

Healthcare-v2009 MRc3:Sustainably sourced materials and products
posted by  Bryan Waters  on 

If one sustainably sourced material category does not reach 10 percentage points, can the deficit be made up by another category if it is in excess of 10%?

3
Mon May 20, 2013, 12:48 pm

Casework

NC-2009 MRc7:Certified Wood
posted by  Benjie Herrera  on 

Kindly advise us to help the casework contractor/manufacturer how to prepare the proper format of invoice as required for LEED Documentation with the following components of casework to be assembl

3
Default Avatar
LEED AP BD+C ,Homes,IDC,OM
LEEDuser Basic Member
17 thumbs up
Sat May 18, 2013, 1:41 am

Building Envelope Commissioning LEED required test methodology

NC-2009 EAc3:Enhanced Commissioning
posted by  Pablo Fortunato Suarez  on 

Our project has included Building Envelope Commissioning as part of the scope of Enhanced Commissioning plan.

2
Fri May 17, 2013, 8:10 pm