LEEDuser’s viewpoint
Frank advice from LEED experts
LEED is changing all the time, and every project is unique. Even seasoned professionals can miss a critical detail and lose a credit or even a prerequisite at the last minute. Our expert advice guides our LEEDuser Premium members and saves you valuable time.
Credit language
© Copyright U.S. Green Building Council, Inc. All rights reserved.
Requirements
Provide an easily-accessible area or areas for the collection and storage of materials for recycling for the entire building in accordance with Section 2.1-5.4.1.2 (and Appendix) of the 2010 FGI Guidelines for Design and Construction of Health Care Facilities. Establish a collection system and controlled areas serving the portion of the building affected by the project dedicated to the separation, storage and collection of materials for recycling including, at a minimum: paper, corrugated cardboard, glass, plastics, metals, batteries and mercury-containing products and devices1.
See all forum discussions about this credit »What does it cost?
Cost estimates for this credit
On each BD+C v4 credit, LEEDuser offers the wisdom of a team of architects, engineers, cost estimators, and LEED experts with hundreds of LEED projects between then. They analyzed the sustainable design strategies associated with each LEED credit, but also to assign actual costs to those strategies.
Our tab contains overall cost guidance, notes on what “soft costs” to expect, and a strategy-by-strategy breakdown of what to consider and what it might cost, in percentage premiums, actual costs, or both.
This information is also available in a full PDF download in The Cost of LEED v4 report.
Learn more about The Cost of LEED v4 »Frequently asked questions
See all forum discussions about this credit »Documentation toolkit
The motherlode of cheat sheets
LEEDuser’s Documentation Toolkit is loaded with calculators to help assess credit compliance, tracking spreadsheets for materials, sample templates to help guide your narratives and LEED Online submissions, and examples of actual submissions from certified LEED projects for you to check your work against. To get your plaque, start with the right toolkit.
Get the inside scoop
Our editors have written a detailed analysis of nearly every LEED credit, and LEEDuser premium members get full access. We’ll tell you whether the credit is easy to accomplish or better left alone, and we provide insider tips on how to document it successfully.
© Copyright U.S. Green Building Council, Inc. All rights reserved.
Requirements
Provide an easily-accessible area or areas for the collection and storage of materials for recycling for the entire building in accordance with Section 2.1-5.4.1.2 (and Appendix) of the 2010 FGI Guidelines for Design and Construction of Health Care Facilities. Establish a collection system and controlled areas serving the portion of the building affected by the project dedicated to the separation, storage and collection of materials for recycling including, at a minimum: paper, corrugated cardboard, glass, plastics, metals, batteries and mercury-containing products and devices1.