Can a credit in one rating system be considered ID in another?
NC-2009 IDc1:Innovation in Designposted by Stantec BG+LU FW on
Can a credit that occurs in one rating system be considered an ID credit in another rating system if there is no equivalent credit? The example: I am using LEED – NC.
Submeter for process uses
CI-2009 EAc3:Measurement and Verificationposted by Shoko Yasuda on
Hello, I am doing CI Retail project (LEED-CI 2009 EAc3 Case 1) and it includes dish washer and ice cube machine. I understand that we have to have sub meters for process loads.
Compliance Path Questions
Healthcare-v2009 IEQc4:Low-emitting materialsposted by Catherine Blakemore on
For each Group, do all products listed have to follow either Path 1 or Path 2? For eample Group 3 offers: Path 1.
High bay Areas LPD
NC-2009 EAp2:Minimum Energy Performanceposted by Saju Varghese on
We are working on a project with a bus repair bay areas for which we considered as "High Bay" areas for the energy model due to the fact that these areas are higher than 25 ft.
more than 1 system to simulate baseline building?
NC-2009 EAc1:Optimize Energy Performanceposted by jaume balana on
Hello, Our project is a two floors and 1300 m2 building, opened to four orientations.
Unmet Load Hours
NC-2009 EAp2:Minimum Energy Performanceposted by Jean Marais on
HVAC plans show the room setpoint. This should be the OPERATIVE temperature.
Raised Floor Wood Components
NC-2009 MRc7:Certified Woodposted by Sonia M. Miranda Palacios on
Hi all, I´m working in a project that will have raised floors with a wood beam (instead of metal) as support. The wood will not be "FSC" certified.
SSc4 - Number of building occupants - 24 hour facility
EBOM-2009 SSc4:Alternative Commuting Transportationposted by Jessica Verhotz on
We are working on a hospital that is a 24-hour facility.
Concrete additives replacing portion of cement
NC-2009 IDc1:Innovation in Designposted by Maya Karkour on
Hello, For one of our LEED projects (50-storey mixed use tower), the full structure will be concrete (slabs and columns).
Existing Envelop is unknow
NC-2009 EAp2:Minimum Energy Performanceposted by Anil Bhari on
As per requirement G3.1.5(f) baseline, any existing envelope, the baseline building design shall reflect existing conditions prior to any revision.