Gas metering
EBOM-2009 EAc3.2:Performance Measurement—System-Level Meteringposted by Oana Stamatin on
In our office building, the annual Gas Consumption accounts for more than 40% of the total annual energy consumption. The gas is used for Heating and for Cooking (for a Restaurant).
To weigh, or not to weigh?
NC-2009 MRc2:Construction Waste Managementposted by Lawrence Lile on
We have a project with some existing asphalt pavement that will be busted up and used as clean fill on the same project.
Data Centers in LEED v3 - exceptional calculation method?
NC-2009 EAp2:Minimum Energy Performanceposted by Jeremy Rapoza on
I have a relatively large data center (200kw connected load) in a relatively larger building (250k sf) so that the data center is not the major program space, but is a relatively large minority of
Catch
NC-2009 EAc6:Green powerposted by Jean Marais on
Are there any catches to proving that the RECs that we buy are used only on a specific LEED project? Should I ask the seller to specify the facility's name or something on the REC?
How can we get feedback on the pilot credit?
Pilot-Credits SSpc82:Local food productionposted by Heather DeGrella on
I am wondering if anyone who has posted has been able to get feedback any other way? I tried submitting my same question via LEEDonline and have received no response.
Fixture Replacement
CI-2009 WEp1:Water Use Reduction—20% Reductionposted by Patrick Salmon on
Our project will be pursuing the thirty percent (30%) savings threshold by including fixtures both within and outside the LEED project boundary.
LEED Interpretation 10372
NC-2009 MRc7:Certified Woodposted by Tristan Roberts on
I don't think the policy it gives is anything new—a lot of us have worked to choose to report wood content as either recycled or FSC, but not both—but FYI, LEED Interpretation 10372 was released on
Pressure Drop adustment in Section 14 Tables
NC-2009 EAp2:Minimum Energy Performanceposted by Omar Elrawy on
Actually I'am not able to correlate section 14 required inputs under pressure drop column "CFMd", and the requirements of ASHRAE TABLE 6.5.3.1.1 B in (pascals/ in.w).
Option 3 Under LEED ND V4
ND-v2009 SLLc2:Brownfields redevelopmentposted by Martine Desbois on
Could you please explain that Option. I am not sure I understand when it is applicable. Thank you OPTION 3.
Clarification on prescriptive option skylight/floor area ratio
NC-2009 IEQc8.1:Daylight and Views—Daylightposted by Jason Levine on
We are in the process of completing the spreadsheet for credit IEQ 8.1 for a NC project. Kalwall skylights are being used, in addition to Solatube 330 DS daylighting systems.