Zoning in Retail

CI-2009 EAc1.3:Optimize Energy Performance—HVAC
posted by  Jan Hesse  on 

I am working on an CI for Retail project. The Retail space will be included in an shopping mall and is three floors high.

6
Default Avatar
MECHANICAL ENGINEER
GE3S ENVIRONMENTAL CONSULTANTS
LEEDuser Basic Member
1 thumbs up
Mon May 18, 2020, 2:01 pm
2
Wed May 15, 2019, 3:43 pm

CI-2009 EAc1.3, Motor Variable Speed Control

CI-2009 EAc1.3:Optimize Energy Performance—HVAC
posted by  David Schaeffer  on 

I am working on a tenant build out where all the equipment is existing, as part of the recent core and shell build.

1
Fri Mar 8, 2019, 4:58 pm

CI-2009 EAc1.3, Option 1 HVAC Efficiency

CI-2009 EAc1.3:Optimize Energy Performance—HVAC
posted by  Joseph Girgenti  on 

beginning design of a LEED 2009 CI project.  Will be replacing AC units so want to spec units with efficiency adequate to meet this requirement.  Requirement references NBI Advanced Build

1
Thu Feb 14, 2019, 4:54 pm

Core Performance Guide Compliane

CI-2009 EAc1.3:Optimize Energy Performance—HVAC
posted by  Patrice McVeigh  on 

Hi All,

We have a CI project and have a query in relation to Core Performance Guide Criteria.  

1
Wed Dec 12, 2018, 8:02 pm
3
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Mar 8, 2018, 9:26 am
0

Appropriate Zoning and Controls Questions

CI-2009 EAc1.3:Optimize Energy Performance—HVAC
posted by  Patrick Salmon  on 

We have an open office VAV project that is only pursuing the "Appropriate Zoning and Controls" portion of Option 1.

1
Tue May 13, 2014, 1:40 pm

Option 1: Equipment Efficiency

CI-2009 EAc1.3:Optimize Energy Performance—HVAC
posted by  Ricardo Sá  on 

Hi, I have several compact rooftop units serving a big sales area. However, only 80% of them is actually new equipment that meet the credit's criteria.

1