Dear All,
I am doing the Energy Model for one of CI Project considering the ASHRAE 90.1.2007 Appendix G - Performance rating method. Tenant space is 12% of overall project's area. Whole building is conditioned by Water cooled chiller. We have created two energy model to compare the cost savings associated with HVAC only.
Baseline Model: Both Project Area and Balance of Modeled Building Segment:
- Envelope - As per ASHRAE 90.1.2007 and Appendix G
- LPD - As per ASHRAE 90.1.2007 and Appendix G
- HVAC System Type (Air Side System) - As per ASHRAE 90.1.2007 and Appendix G
- HVAC System Type (Chiller Plant) - As per ASHRAE 90.1.2007 and Appendix G
- Fan power - As per ASHRAE 90.1.2007 and Appendix G
- Pumps & Cooling Tower - As per ASHRAE 90.1.2007 and Appendix G
Proposed Design:Project Area
- Envelope - Design Proposed
- LPD - Design Proposed
- HVAC System Type (Air Side System) - Design Proposed
- HVAC System Type (Chiller Plant) - Design Proposed
- Fan power - Design Proposed
- Pumps & Cooling Tower - Design Proposed
Proposed Design:Balance of Modeled Building Segment
- Envelope - As per Proposed Envelope. (Details are available)
- LPD - As per ASHRAE 90.1.2007 and Appendix G (Details are not available)
- HVAC System Type (Air Side System) - As per ASHRAE 90.1.2007 and Appendix G (Details are not available)
- HVAC System Type (Chiller Plant) - Design Proposed
- Fan power - As per ASHRAE 90.1.2007 and Appendix G (Details are not available)
- Pumps & Cooling Tower - Design Proposed
- Whether the above approach is correct to arrive the savings to attain 5 or 10 points under EA Cr 1.3 HVAC?
- Whether the above baseline is called Alternate baseline? Since,whole baseline model is created with As per ASHRAE 90.1.2007 only instead of existing design.
- Fresh air and no of people has designed only for project space. For rest of spaces, Fresh air and no of people has provided as per 62.1.2007. Is this correct