Indoor air quality test methods for PM2.5 and PM10
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Tyler Zhu on
From my understanding, in order to pass the test for PM2.5 and PM10, EPA Compendium Method IP-10 has to be used.
Contiguous area requirement removed in the air quality testing section
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Bo White on
Per ID#ad-100000891 and the Credit Language, the "contig
COVID-19 restrictions alternative documentation path
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Esteban Martinez on
Hello,
AHU Prefilters MERV Requirement
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Teaaron Frye on
On a project that we are finishing up the AHU has two sets of filters - MERV 8 prefilter then a MERV 13 main filter. Are the prefilters required to be MERV 13 as well?
New Filters Before Occupancy
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Jalal Avades on
IEQ-C3.2 and IEQ-C5 requires that new sets of filters need to be installed prior to Occupancy. If the project is pursuing both credits do we need to change the filters prior to the Flush out (IEQ-C
Flush Out Path 2 - Fitness center/ Office
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Crina Bosch on
I am working on a fitness center project and the team would like to follow Enhanced Commisioning Path 2: Flush-out.
Flush-out - Hotel Facility
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Luis Andrade on
Hello,
I'm currently working in a project that is a hotel facility.
Amount of Testing Locations
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by cristina algaze beato on
Greetings: We will be seeking this credit through Air Testings. In our case the amount of separate ventilation systems is the one that will determine the amount of air testing locations.
Formaldehyde levels too high in ONE room
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Jenni Betancourt on
For a current higher education project, they performed the Air Testing and it shows everything in compliance except for one room showed a level out of compliance for Formaldehyde.