NC-2009 EAc5:Measurement and Verificationposted by Barbara Aguirre Garcia on
For credit, is it necessary to make calculations within the plan, regarding the baseline calculation, the reporting period? Or is it just describing the elements to do the calculations?
EAc5 Points
NC-2009 EAc5:Measurement and Verificationposted by Jeannie Rueter on
Just trying to understand how the points are awarded for this credit. Option 3 is worth 1 point. Either option 1 or 2 are worth 3 points?
Phased project implementation
NC-2009 EAc5:Measurement and Verificationposted by Tim Murray on
We have a phased higher education project in which a new building addition will be built first, then the existing buildings will be renovated and open a year later.
Is Manual Measurement acceptable?
NC-2009 EAc5:Measurement and Verificationposted by Summer on
I would like to clarify if manual measurement is acceptable and compliant in this credit. We have a project that has BMS or building management system that can only monitors the HVAC consumption.
why only a plan and not a final report after M&V?
NC-2009 EAc5:Measurement and Verificationposted by ANNE JURAN on
To earn this credit all we submit is the plan which basically says we're going to recalibrate and we'll deal with any problems later, right? Is there any backcheck from GBCI on this?
Sharing data on energy star
NC-2009 EAc5:Measurement and Verificationposted by Omar Elrawy on
Dear all,
Direct vs indirect measurements
NC-2009 EAc5:Measurement and Verificationposted by Cesar Ruiz on
Hi everyone, We are working on a Residential New Construction Project, compound of more than 100 apartments, pursuing Option D - Calibrated Simulation.
IPMVP Option D+ PV System
NC-2009 EAc5:Measurement and Verificationposted by Nasim Mirian on
Hello,
LEED v.2009 NC EA Credit 5
NC-2009 EAc5:Measurement and Verificationposted by Andrew Buck on
We are designing a Hotel with the following systems: