Can Low missission gas generator qualify for EAc2?

NC-2009 EAc2:On-site renewable energy
posted by  Mahbuba Khan AIA, LEED AP BD+C  on 

I am doing a factory building in Dhaka Bangladesh. To offset the power outage, they are going to use gas generator.

1
Tue Apr 23, 2013, 4:14 pm

Waste Heat Recovery Boiler

NC-2009 EAc2:On-site renewable energy
posted by  SAMY Chamy  on 

Dear All:- we have two waste recovery boiler to fulfil the steam needed.

1
Wed Jan 6, 2016, 2:57 pm
1
Mon Jun 14, 2010, 5:48 pm

Transpired Solar Collector

NC-2009 EAc2:On-site renewable energy
posted by  Tyler Barter  on 

For an upcoming project we are proposing using a metal wall system that acts as a transpired solar collector to bring preheated air into the building.

1
Tue Apr 17, 2012, 2:33 pm

Biomass Qualifications

NC-2009 EAc2:On-site renewable energy
posted by  Anthony Schoen  on 

We are currently starting a project that utilizes a biomass central steam plant. This plant uses wood chips, a waste product from local paper factories.

1
Wed Jul 10, 2013, 1:30 pm

LEED exam question

NC-2009 EAc2:On-site renewable energy
posted by  Farah A.  on 

A project team is looking to pursue an ID credit on their new office building. The annual building energy cost for their 400,000 square foot project is $15,120.

1
Sun Feb 23, 2014, 9:47 pm

Commissioning of PV system by different commissioning agent

NC-2009 EAc2:On-site renewable energy
posted by  Deborah Lucking  on 

We have had this question come up a few times - the owner and the PV system supplier believe that it can be commissioned by a different commissioning agent.

1
Mon May 1, 2017, 1:06 pm

Eligibility of Wood

NC-2009 EAc2:On-site renewable energy
posted by  Jens Apel  on 

This is a more general question about the eligibility of wood as renewable fuel. Following the Reference Guide I get the impression that all wood apart from untreated waste and mill residue is inel

1
Sat Apr 23, 2011, 5:28 pm

Windmill

NC-2009 EAc2:On-site renewable energy
posted by  SAMY Chamy  on 

Dear Concern:- Our client produce huge amount of Renewable energy by wind mills and the energy produced via wind mill is almost 5 times greater than LEED project annual energy consumption so please

3
Enginneer
T&T Green
LEEDuser Basic Member
9 thumbs up
Mon May 1, 2017, 1:01 pm

Wood pellets as a Renewable energy source

NC-2009 EAc2:On-site renewable energy
posted by  Vassil Vassilev  on 

We are at conceptual design stage for a new school building.

5
Wed Sep 28, 2016, 3:09 am