Forum quick links
Reduced Runoff/Rate of Runoff for existing site
NC-2009 SSc6.1:Stormwater Design—Quantity Controlposted by R.L. Bowen on
Our premilimary review comments for V2009 noted that "Reduction in quantity (SSc6.1) will require stormwater to be infiltrates or re-used onsite.
Stormwater harvesting for car washing
NC-2009 SSc6.1:Stormwater Design—Quantity Controlposted by Margarita Zaritskaya on
Hi all,
SS 6.1 Case 2 options?
NC-2009 SSc6.1:Stormwater Design—Quantity Controlposted by Karen Joslin on
Has anyone been successful applying the impounding/receiving stream protection approach for a previously >50% impervious site?
Stormwater Management
NC-2009 SSc6.1:Stormwater Design—Quantity Controlposted by Divantha Ekanayake on
The project I’m referring to is a LEED 2009 New Construction project, and has already been sent for the design review and received back with review comments.
No file uploads?
NC-2009 SSc6.1:Stormwater Design—Quantity Controlposted by Carly Ruggieri on
A recently registered project of mine has the most updated version (5.0) of the credit forms for SSc6.1.
Eligibility for case 1 option 2
NC-2009 SSc6.1:Stormwater Design—Quantity Controlposted by tomaz kipnis on
Hi, The requirements for Option 2 (case 1) of this credit refer to the protection of receiving stream channels.
Storm Interval and Drawdown
NC-2009 SSc6.1:Stormwater Design—Quantity Controlposted by Leandro Silva on
Thank you for all of the information provided on this forum. I am confident in all of our calculations up to the Storm Interval and Drawdown calculations.
Discharge rates and run off
NC-2009 SSc6.1:Stormwater Design—Quantity Controlposted by Sean Hogan on
Hi, In simple terms, is there a difference between 'discharge rate' and 'run off'? We are currently assessing our site to determine which case and path to follow.
How to show 100% Infiltration
NC-2009 SSc6.1:Stormwater Design—Quantity Controlposted by Kenneth Bailey on
Our project is the only development on a small, flat, island. The surface is sand or sandy topsoil and is extremely porous.
A building on a campus
NC-2009 SSc6.1:Stormwater Design—Quantity Controlposted by Lisa Sawin on
We currently working on a project that will be pursuing LEED certification. The building resides on a campus but we are only certifying one building as part of our contract.