A recently registered project of mine has the most updated version (5.0) of the credit forms for SSc6.1. I noticed on this version of the form, there are no file uploads necessary for the credit anymore (Option 1, Case 2). We can just document compliance by plugging in one value for pre-development quantity and one value for post-development quantity without showing where the values came from or how they were calculated. I'm finding it hard to believe that the reviewers will be able to approve a credit based on two values with no backup documentation. Is this a mistake on the updated version of the form?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Michael DeVuono
Regional Stormwater LeaderArcadis North America
LEEDuser Expert
187 thumbs up
June 7, 2013 - 9:30 am
I wold take your question directly to GBCI:
http://www.gbci.org/org-nav/contact/Contact-Us/Project-Certification-Que...
Kathryn West
LEED AP BD+C, O+M, Green Globes ProfessionalJLL
154 thumbs up
June 7, 2013 - 10:39 am
you will DEFINITELY be asked for calculations!!!
Samuel Sura
Mre-Dome
March 19, 2015 - 8:54 am
If the reviewers wanted to see the calculations why would they not keep a part of the credit form?
Can anyone confirm if the calculations were additionally requested?
emily reese moody
Sustainability Director, Certifications & ComplianceJacobs
LEEDuser Expert
476 thumbs up
September 11, 2018 - 4:50 pm
Has anyone seen this happen and have more insight? I have a project asking me the same question...