Thank you for all of the information provided on this forum. I am confident in all of our calculations up to the Storm Interval and Drawdown calculations. If I understand things correctly, the calculations are fairly simple:

Example
Storm volume: 119,000 liters
Storage Capacity: 148,000 liters
Dawdown Rate (reuse): 2,300 liters/day

Storage + (drawdown x 3 days) - Storm volume = capacity remaining (or runoff)

Storm 1
148,000 + 6,900 - 119,000 = 35,900 storage remaining after three days.

Storm 2
Storm volume - Capacity remaining - drawdown (1 day) = Runoff

119,000 - 35,900 - 2,300 = 80,800 liters of runoff (post-dev)

Assuming a fairly impervious Pre-dev site condition let´s assume a calculated runoff of 115,000 liters per 2 year 24 hour storm:

Pre-dev runoff: 115,000 liters
Post-dev runoff: 80,800 liters
Runoff reduction: 34,200 liters
Runoff reduction: 30%

Is it that easy? Am I missing something?