Forum quick links
Required Materials for LCA
NC-v4 MRc1:Building life-cycle impact reductionposted by RDK E&S on
Hello,
We are looking for more information as to what details from Baseline and Proposed models need to be included in the models.
core and shell data center
Data-Centers-NC-v4 EAp2:Minimum energy performanceposted by Amgad Khattab on
Hi everyone,
Pest management
EBOM-v4 EQc9:Integrated pest managementposted by VISHESH AGARWAL on
I am working on the project where it is difficult to use SF Tier-3 pesticide as per the LEED Norms.
how are points dealt with when there is no cooling tower
EBOM-v4 WEc3:Cooling tower water useposted by Raquel Viula on
Hello, would anyone know if, in EBOM v4, the points for the WE credit: Colling Tower Water Use get filtered out from the LEED score calculation or are gained by default, when there
Colocation Data Center
Data-Centers-NC-v4 EAp2:Minimum energy performanceposted by David Edenburn on
In the minimum energy performance calculator, the first tabs are about the servers. I have a "colo" data center, the empty data halls are rented out to clients, essentially tenants.
SRI value for all paving materials are requested, where to find concrete SRI values?
NC-v4 SSc5:Heat island reductionposted by Milo Aguilar on
Design reviewer suggested to Refer to LEED Interpretation 10411 for a listing of standard nonroof materials in lieu of project-specific testing data, if applicable. But have not been able
Reused materials from project site - burned trees and stone
NC-v4 MRc3:Building product disclosure and optimization - sourcing of raw materialsposted by Kevin Gilleran on
Good Day,
Providing a Link to Label instead of an actual certificate?
NC-v4 EQc2:Low-emitting materialsposted by Azra on
Hello all,
Daylighting for Light Industrial
CS-v4 EQc4:Daylightposted by Troy Glasner on
Hi, I am helping a client, they have a light industrial project that has a workshop in the back area and an office mezzanine.