Demolishing an existing school with asbestos
Schools-NC-v4 MRc5:Construction and demolition waste managementposted by Priscillia Champagne on
We are currently working on a school project that will be completed in several phases. An existing school is located on the project site and will be occupied until the new building is constructed.
Monthly Evapotranspiration Rate
NC-v4 WEp1:Outdoor water use reductionposted by Ahmed Labeeb on
Dear,
No residential buildings
NC-v4 LTc4:Surrounding density and diverse usesposted by Zeynep Cakir on
Our project is located in an organized industrial zone.
Existing base building fixtures
CI-v4 EQc6:Interior lightingposted by Omar Elrawy on
We have an interior fit-out project, in which we are trying to comply with Option 2 (A, B, C, and D)
Pre-selected sites, can a project still opt for Integrative Process credit?
NC-v4 IPc1:Integrative processposted by Nermin Hegazy on
We are studying the feasibility of acheiving LEED certification for a series of floors in an office building.
Shared Heat Pump System for Group Project - Is This DES?
NC-v4 EAp2:Minimum energy performanceposted by Aaron Yorke on
Hello everyone,
LEED Online is not displaying Reginal Priority credit category
NC-v4 RPc1:Regional priorityposted by Norbert Harmathy on
Hello,
We registered a new project under LEED v4 NC. In ALL Credit categories listed, there is NO Regional Priority credit category.
Can we certify only the administrative building in a pharmaceutical factory project?
NC-v4 MPR2:Must use reasonable LEED boundariesposted by Amgad Khattab on
We have a pharmaceutical factory project consists of the following buildings: -
1. An administrative building (Ground + 3).
2. A Production building (Ground +2).
Group Project Scoring
EBOM-v4 EAc7:Renewable energy and carbon offsetsposted by Andy Rhoades on
How do I score EAc7 when certifying for a group project? I have the VER proposals for the three buildings but don't know how to score them together. Thanks!
Remediation of LEED Project Area or only disturbed areas
NC-v4 LTc3:High priority siteposted by Mark Meaders on
We have a project that has had a Phase 1 and II ESA performed. It found there was acetone and mercury on site.