Forum quick links
Net Zero Data Center
NC-v4 EAc2:Optimize energy performanceposted by Amal Venugopal on
Hi All,
Greetings!..
Developer-Sponsored Transit Frequency
ND-Plan-v4 NPDc8:Transportation demand managementposted by Gabriela Mesquita on
ND-Plan-v4 NPDc8 - Transportation demand management
Non-certified buildings in LEED boundary
NC-v4 MPR2:Must use reasonable LEED boundariesposted by chila chila on
Hi everyone,
Sidewalks width
ND-Plan-v4 NPDp1:Walkable streetsposted by Gabriela Mesquita on
Hello, I have a query.
In the Walkable Streets Prerequisite, specifically at point C.
Pass air method
NC-v4 EQp1:Minimum indoor air quality performanceposted by Alex Edwards on
Hello!
Thanks for everyone's help, I have a question about the pass air method
Core and Shell
CS-v4 EAp1:Fundamental commissioning and verificationposted by Bryan Markkanen on
We have a Core & Shell project that is complete but doesn't have tenants. The owner is having problems getting tenants (and their layouts/ HVAC needs) so we don't have a way to test the e
Scope
CI-v4 EAc5:Enhanced refrigerant managementposted by Michael Smithing on
For a CI project with minimal new HVAC equipment is the credit scope limited to equipment within the scope of the project only, or is there a hurdle below which base building equipment must comply
chemical storage cabinet
NC-v4 EQc1:Enhanced indoor air quality strategiesposted by Erik Heuler on
Hello,
Preschool child toilet rooms - no urinals
NC-v4 WEp2:Indoor water use reductionposted by Lyle Axelarris on
I'm working on a child care center project, with many toilet rooms designed for preschool-aged children. Since urinals are not appropriate for this occupancy type, should I consider these res
Base building energy sources
CS-v4 EAc3:Advanced energy meteringposted by Ciaran McCabe on
Hi, I just require come clarification on the Base Build systems.